Key Takeaways
- Governing Scope: Construction Law No. 135/2025/QH15; Ministry of Construction Circular No. 34/2026/TT-BXD dated 25/06/2026 (Clauses 1 and 2, Article 2.
- Key Benchmark: Under Clauses 1 and 2, Article 2 of Circular No.
- Execution Control: Cite exact document page coordinates and regulatory table items for each similar-contract grade determination.
01Regulatory Context & Core Scope
During works E-HSDT evaluations, a recurring analytical flaw occurs when evaluators speculate about building story counts, structural height, or total floor area to assign a structural grade even though the bid package contains no design drawings, appraisal notices, or construction permits. Guesswork of that kind risks unjustly downgrading a compliant reference contract or arbitrarily inflating project grades without documentary proof.
02Qualification Benchmarks & Bidder Preferences
Under Clauses 1 and 2, Article 2 of Circular No. 34/2026/TT-BXD, an independent structure is graded across both Annex I (importance and functional capacity) and Annex II (structural scale), taking the highest resulting grade. Where the reference contract and acceptance certificate identify a facility explicitly covered by Annex I, such as administrative headquarters, schools, hospitals, or capacity-rated utilities, evaluators must check Annex I functional tables first before invoking Annex II.
For example, Item 1.1.7 of Table 1.1 in Annex I of Circular No. 34/2026/TT-BXD classifies commune-level Party Committee, People's Council, and People's Committee offices as Grade III while leaving Grade IV blank. Even when a bid omits structural drawings or building permits, evaluators must never assume a one-story or two-story structure to downgrade that office into Grade IV under Annex II and reject the contractor's reference experience.
03Procedural Sequence & e-GP Execution
Conversely, where contract and handover certificates lack sufficient Annex I functional parameters and require structural-scale verification under Annex II, such as building height, floor count, span, or gross floor area, panels must refrain from guessing and invoke Article 30 of Decree No. 214/2025/ND-CP. The investor should send an e-GP clarification request asking the bidder to supply pre-closing project approvals, construction permits, or as-built drawings establishing structural scale.
Every building-grade determination recorded in the evaluation report must cite exact source coordinates, including approval decision numbers, scanned acceptance page numbers, and applicable circular table items. Grounding every finding in verifiable records prevents bidder petitions rooted in unsupported assumptions.
Evidence Rules to Prevent Building-Grade Speculation in Bid Evaluation
- Check Annex I of Circular No. 34/2026/TT-BXD first whenever contracts and handover minutes clearly identify a listed functional facility.
- Never estimate story counts, heights, or floor areas to assign grades without supporting drawings or permits.
- Issue an e-GP clarification notice under Article 30 of Decree No. 214/2025/ND-CP when pre-closing structural-scale proof is required.
- Cite exact document page coordinates and regulatory table items for each similar-contract grade determination.
Legal Basis & Regulatory Scope
Construction Law No. 135/2025/QH15; Ministry of Construction Circular No. 34/2026/TT-BXD dated 25/06/2026 (Clauses 1 and 2, Article 2; Item 1.1.7 of Table 1.1, Annex I; Annex II); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 29 and 30); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025.