Key Takeaways
- Governing Scope: Decision 42/QD-TTg dated 27 March 2025 of the Prime Minister; Bidding Law 22/2023/QH15.
- Key Benchmark: Written explanation citing Decision 42/QD-TTg dated 27 March 2025 and confidentiality clauses in the underlying contract.
- Execution Control: Functional building-grade verification under Item 1.1.7, Table 1.1, Annex I of Circular 06/2021/TT-BXD based on facility name and use.
01Regulatory Context & Core Scope
Contractors that previously built police stations or internal security facilities often face clarification bottlenecks when bidding on civil works packages. Evaluation panels routinely request full floor plans or internal investment approval decisions to verify building grades, yet statutory state-secret laws strictly prohibit circulating classified design documents on public portals or to third parties.
02Security Validity & Commitment Scope
On 27 March 2025, the Prime Minister issued Decision 42/QD-TTg establishing the List of State Secrets in national security, social order, and public safety. This decision provides explicit legal grounds for identifying which project records, site layouts, and security-agency construction dossiers fall under Top Secret, Secret, or Confidential classifications.
To substantiate prior experience validly under Decree 24/2024/ND-CP and Circular 22/2024/TT-BKHDT without breaching confidentiality, bidders should cite Decision 42/QD-TTg alongside the non-disclosure clauses of the completed contract. Acceptable non-classified evidence comprises the executed construction contract, priced bills of quantities, completion acceptance minutes, and VAT invoices.
03Contract Performance, Settlement & Amendments
When verifying building grades for public authority headquarters, evaluation panels should apply the primary functional classification rule under Clauses 1 and 2, Article 2 and Item 1.1.7, Table 1.1, Annex I of Circular 06/2021/TT-BXD. Panels must rely on the verified facility name and acceptance records without guessing structural height under Table 1.2 or demanding classified blueprints.
Within permissible non-classified files, panels should cross-check completion dates on acceptance minutes against electronic VAT invoice timestamps to confirm authentic contract execution. This balanced evidence protocol honors state-secret safeguards under Decision 42/QD-TTg while assessing genuine contractor capability fairly.
Valid Evidence Package for State-Secret Similar Contracts
- Written explanation citing Decision 42/QD-TTg dated 27 March 2025 and confidentiality clauses in the underlying contract.
- Executed construction contract and bill-of-quantities summary demonstrating relevant scope without disclosing classified layouts.
- Completion and handover acceptance minutes paired with matching electronic VAT invoices.
- Functional building-grade verification under Item 1.1.7, Table 1.1, Annex I of Circular 06/2021/TT-BXD based on facility name and use.
Legal Basis & Regulatory Scope
Decision 42/QD-TTg dated 27 March 2025 of the Prime Minister; Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP; Circular 22/2024/TT-BKHDT; Clauses 1 and 2 of Article 2 and Table 1.1 of Annex I of Circular 06/2021/TT-BXD.