Key Takeaways
- Governing Scope: Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Forms 3A and 4A).
- Key Benchmark: Where legacy consortium split documents are omitted, the Procuring Entity should request clarification under Article 28 of Decree 24/2024/ND-CP before disqualifying.
- Execution Control: Issue an Article 28 clarification request if past consortium agreements lack verified split or invoice evidence.
01Regulatory Context & Core Scope
When contractors form a joint venture to bid on large construction or goods packages, assessing each member's similar-contract threshold is a frequent source of evaluation errors. Under Chapter III of Forms 3A and 4A issued with Circular 06/2024/TT-BKHDT, total joint venture capacity equals the sum of its members, provided every partner meets the requirement corresponding to its specific assigned scope.
02Pricing Methodology & Cost Controls
Evaluation starts from the signed Joint Venture Agreement inside the E-HSDT, which must itemize each partner's work scope, percentage split, and estimated contract share aligned with the bid price schedule. If the lead partner handles 60% of civil works and the second partner handles 40%, each must prove similar-contract experience covering at least 60% and 40% respectively of the E-HSMT baseline.
Panels must inspect prior contracts where a joint venture partner previously served as a consortium member or subcontractor. Under Circular 06/2024/TT-BKHDT evaluation rules, only the portion directly executed and accepted by that member counts toward its experience total, never the full aggregate contract sum of the earlier consortium.
03Qualification Benchmarks & Bidder Preferences
For construction packages governed by structural types and building grades under Circular 06/2021/TT-BXD, each partner performing primary structural trades must prove experience at or above the tendered building grade for its assigned trade. An E-HSMT must never force every member to satisfy 100% of total package capacity individually, nor allow one member's unrelated civil experience to mask another partner's lack of specialized scope experience.
During detailed scoring, the evaluation panel should cross-check percentages across the Joint Venture Agreement, priced BOQ breakdown, acceptance minutes, and VAT invoices for each submitted contract. Where legacy consortium split documents are omitted, the Procuring Entity should request clarification under Article 28 of Decree 24/2024/ND-CP before disqualifying.
Joint Venture Similar-Contract Verification Checklist
- Reconcile work scope and percentage splits between the Joint Venture Agreement and the bid price schedule.
- Verify each member meets similar-contract thresholds matching both the percentage and technical nature of its share.
- Credit only the member's own executed portion when reviewing past consortium or subcontracting credentials.
- Issue an Article 28 clarification request if past consortium agreements lack verified split or invoice evidence.
Legal Basis & Regulatory Scope
Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Forms 3A and 4A); Circular 06/2021/TT-BXD dated 30 June 2021.