Distinguishing Standalone Similar Works Contracts From Aggregated Small Items in Evaluation

Distinguishing Standalone Similar Works Contracts From Aggregated Small Items in Evaluation
Clarifying works similar-contract evaluation rules under Circular 22/2024/TT-BKHDT: why small contracts cannot be aggregated to satisfy a standalone graded structure.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP.
  • Key Benchmark: Confirm whether E-HSMT Chapter III defines the package as a single standalone structure or a multi-structure cluster.
  • Execution Control: Credit only the bidder own executed value when the reference contract was performed via consortium or subcontract.

01Regulatory Context & Core Scope

During construction bid evaluation, contractors frequently submit five or six small maintenance contracts whose summed value meets the threshold in place of one complete graded structure. Accepting blind value aggregation compromises technical vetting for complex structural work, whereas rejecting valid multi-component combinations on mixed infrastructure packages risks improper disqualification.

02Core Regulatory Provisions & Conditions

Under the works E-HSMT templates of Circular 22/2024/TT-BKHDT and Decree 24/2024/ND-CP, similar-contract evaluation turns strictly on whether the tendered package comprises a single standalone structure or an integrated cluster of distinct structures.

Where a package involves one standalone facility, each required reference structure must be substantiated by a single qualifying contract matching the structural type and construction grade under Circular 06/2021/TT-BXD while reaching the minimum construction value ratio. Bidders cannot stitch together smaller sub-threshold or lower-grade contracts to substitute for a standalone graded structure.

03Evaluation Criteria & Documentary Proof

Conversely, where a package combines distinct structures such as an administration block, internal access roads, and drainage lines, E-HSMT Chapter III sets separate reference criteria per component. Bidders may then qualify either through one comprehensive contract containing all components or through separate compliant contracts matched to each component structure.

Furthermore, where a bidder performed prior reference work as a consortium member or subcontractor, panels may credit only the contract value and structural scope directly executed by that bidder under verified consortium agreements and itemized acceptance minutes.

Checklist for Auditing Works Similar Contracts in E-HSDT

  • Confirm whether E-HSMT Chapter III defines the package as a single standalone structure or a multi-structure cluster.
  • Reject attempts to aggregate small or lower-grade contracts to meet a standalone structure requirement.
  • Verify matching structural class and construction grade under Circular 06/2021/TT-BXD from official acceptance records.
  • Credit only the bidder own executed value when the reference contract was performed via consortium or subcontract.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP; Circular 22/2024/TT-BKHDT (taking full effect on 1 January 2025); Circular 06/2021/TT-BXD.

Filed under: Bid Evaluation & Award #Similar Contracts #Standalone Facility #Multi-Structure Project #Building Grade
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.