Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Clause 3, Article 44); Govern.
- Key Benchmark: The controlling legal authority against competition-restricting E-HSMT provisions rests on Clause 3, Article 44 of Law No.
- Execution Control: Eliminate geographic restrictions, client-type filters, or overly narrow sub-item conditions that curtail competition.
01Regulatory Context & Core Scope
A frequent error triggering bidder petitions and audit findings in works tenders is inflating experience thresholds above the actual complexity of the project. For instance, although an approved civil or infrastructure project falls under Grade IV, some E-HSMT drafts demand similar contracts and site commander credentials from Grade III or higher. Such over-specification directly breaches statutory principles of fairness and open competition.
02Qualification Benchmarks & Bidder Preferences
The fixed rule for Chapter III of every works E-HSMT is straightforward: the package may require similar completed contracts and key personnel experience only at the building grade of the package works or higher. A Grade IV package may require Grade IV or higher and must never escalate the threshold to Grade III; likewise, a Grade III package sets the floor at Grade III or higher rather than demanding Grade II.
The controlling legal authority against competition-restricting E-HSMT provisions rests on Clause 3, Article 44 of Law No. 22/2023/QH15, Clause 5, Article 26 of Circular No. 79/2025/TT-BTC, and Clause 1, Article 29 of Decree No. 214/2025/ND-CP. If an E-HSMT inserts inflated grade thresholds or hyper-granular sub-item mandates designed to narrow participation, those unlawful requirements cannot legally serve as grounds to reject bids.
03Effective Dates & Transitional Scope
Following the entry into force of Circular No. 34/2026/TT-BXD on 01/07/2026, E-HSMT drafters must verify the controlling building grade against approved design records and the transitional rules in Article 5 before entering criteria on the e-GP webform. Alongside preserving the correct grade floor, drafters must refrain from bundling unrelated work types outside package scope or restricting reference contracts to a single locality.
Before presenting an E-HSMT for investor approval, independent appraisal teams should reconcile three sources: the approved investment decision or economic-technical report, the building-grade determination under Circular No. 34/2026/TT-BXD or applicable prior rules, and the e-GP qualification fields for similar contracts and key staff. Tight alignment across those records shields the investor from valid petitions while sustaining healthy market competition.
Checklist for Legally Valid Building-Grade Criteria in E-HSMT
- Confirm the exact building type and grade directly from the approved investment decision or economic-technical report.
- Set similar-contract thresholds strictly at the package's actual building grade or higher without upward escalation.
- Align key personnel experience requirements with the applicable building grade under Decree No. 175/2024/ND-CP.
- Eliminate geographic restrictions, client-type filters, or overly narrow sub-item conditions that curtail competition.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Clause 3, Article 44); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 1, Article 29); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025 (Clause 5, Article 26); Ministry of Construction Circular No. 34/2026/TT-BXD dated 25/06/2026 (effective 01/07/2026).