Drafting E-HSMT for Routine Road, Urban Drainage, and Public Street Lighting Maintenance Packages

Drafting E-HSMT for Routine Road, Urban Drainage, and Public Street Lighting Maintenance Packages
Guidance on classifying recurrent public-utility maintenance tenders under Decree 32/2019/ND-CP and Circular 79/2025/TT-BTC, setting emergency response criteria and volume-based payment terms.

Key Takeaways

  • Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Clause 3, Article 44); Government Decree No. 32/2019/ND-CP .
  • Key Benchmark: In Chapter III qualification criteria, drafters must uphold open competition under Clause 3, Article 44 of Law No.
  • Execution Control: Align monthly or quarterly acceptance certificates with patrol logs and worker safety compliance records.

01Regulatory Context & Core Scope

Routine maintenance packages covering road pavements, urban stormwater drainage desilting, and public street-lighting operation typically draw from annual recurrent state budgets. A recurring threshold question for municipal procuring entities is classifying the package correctly as non-consulting services versus civil works in order to select the right e-GP E-HSMT model.

02Pricing Methodology & Cost Controls

Under Government Decree No. 32/2019/ND-CP dated 10/04/2019 governing public service commissioning and tendering from recurrent budgets, municipal road, drainage, and street-lighting upkeep favors open competitive bidding whenever statutory criteria are met. Under Circular No. 79/2025/TT-BTC, package classification turns on the dominant cost share: packages centered on scheduled patrolling, gully cleaning, lighting timer operation, and routine lamp swaps follow non-consulting forms, whereas packages dominated by structural asphalt patching, culvert replacement, or underground cable laying follow works forms.

In Chapter III qualification criteria, drafters must uphold open competition under Clause 3, Article 44 of Law No. 22/2023/QH15 and Clause 5, Article 26 of Circular No. 79/2025/TT-BTC. In particular, E-HSMTs must not require bidders to own an office or equipment yard within the local district before bid opening, permitting instead post-award mobilization commitments that meet target emergency response times.

03Core Regulatory Provisions & Conditions

Chapter V technical specifications should establish measurable service-level response standards: maximum dispatch times to clear flooded storm drains, emergency isolation and repair deadlines for severed underground cables or tripped lighting cabinets at night, traffic-control barrier plans, and valid electrical-safety certifications for aerial-bucket technicians.

For contracting and payment controls, predictable year-round patrol and preventive schedules suit fixed-unit or lump-sum utility pricing, while reactive repairs for traffic-damage or sudden pavement subsidence should use fixed-unit BOQ items verified via daily patrol logs and site acceptance certificates.

Checklist for Urban Road, Drainage, and Lighting Maintenance E-HSMT

  • Classify the tender accurately as non-consulting services or works by primary cost weight under Circular No. 79/2025/TT-BTC.
  • Eliminate restrictive pre-bid requirements mandating local offices or pre-existing district equipment yards.
  • Quantify emergency dispatch SLAs for flood clearing, nighttime lighting outages, and road-traffic safety controls in Chapter V.
  • Align monthly or quarterly acceptance certificates with patrol logs and worker safety compliance records.

Legal Basis & Regulatory Scope

Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Clause 3, Article 44); Government Decree No. 32/2019/ND-CP dated 10/04/2019; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 1, Article 29); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025 (Clause 5, Article 26).

Filed under: E-HSMT & Budgeting #Infrastructure Upkeep #Lighting & Drainage #Decree 32/2019 #E-HSMT
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.