Reviewing Preference Eligibility and Proportionate Similar-Contract Criteria for Micro and Small Enterprises in Late 2026

Reviewing Preference Eligibility and Proportionate Similar-Contract Criteria for Micro and Small Enterprises in Late 2026
How to verify micro and small enterprise status under Decree 80/2021/ND-CP, apply the 5 billion VND works set-aside, and calibrate similar-contract values under Circular 79/2025/TT-BTC.

Key Takeaways

  • Governing Scope: Point e of Clause 1, Points a and dd of Clause 2, and Point d of Clause 3, Article 10 of Bidding Law 22/2023/QH15 (as amended by Law 90/2025/QH15); Clause 2 of Artic.
  • Key Benchmark: Where scores tie in domestic works packages, micro and small enterprises also receive higher ranking priority under Point a, Clause 2, Article 10.
  • Execution Control: Accept two immediately lower-grade works each at 50% or higher value, or waive prior-contract criteria where permitted for simple packages.

01Regulatory Context & Core Scope

Late-year public spending brings numerous maintenance, renovation, and local supply tenders suited for micro and small enterprises. To broaden genuine competition without sacrificing delivery capability, E-HSMT drafters should apply micro and small enterprise rules accurately under Article 10 of Bidding Law 22/2023/QH15 and Article 8 of Decree 214/2025/ND-CP while calibrating similar-contract requirements proportionately.

Under Point dd, Clause 2 and Point d, Clause 3, Article 10 of the Bidding Law alongside Clause 2, Article 8 of Decree 214/2025/ND-CP, domestic construction works packages valued at up to 5 billion VND (5,000,000,000 VND) are reserved for micro and small enterprises.

02Core Regulatory Provisions & Conditions

Other enterprise sizes may participate only upon retendering after no micro or small enterprise meets requirements. Where scores tie in domestic works packages, micro and small enterprises also receive higher ranking priority under Point a, Clause 2, Article 10.

To verify bidder eligibility under Section 5.1 E-BDL of Template 3A, evaluators classify enterprise size under Article 5 of Decree 80/2021/ND-CP using primary sector, annual average social-insurance headcount, and prior-year revenue or total capital. In industry and construction, micro enterprises employ up to 10 workers with revenue or capital up to 3 billion VND, while small enterprises employ up to 100 workers with revenue up to 50 billion VND or capital up to 20 billion VND; in trade and services, small enterprises employ up to 50 workers with revenue up to 100 billion VND or capital up to 50 billion VND.

03Qualification Benchmarks & Bidder Preferences

When drafting similar-contract thresholds under Chapter III of Template 3A in Circular 79/2025/TT-BTC, Footnote (13) sets standard contract value around 50% of package construction value, or 40% to 50% for specialized work or regions with limited local contractor capacity. E-HSMTs cannot stack item-level similarity requirements inside a full structure and must honor the rule allowing two completed structures of the immediate lower grade each valued at least 50% to satisfy one required structure.

For simple maintenance, supply, or small works packages, Circular 79/2025/TT-BTC templates also let the Project Owner select Not Applicable for similar-contract experience, or scale down turnover and contract requirements under Clause 4, Article 35 when standard metrics would yield fewer than three qualified bidders, provided the submission documents the rationale.

SME & Micro-Enterprise Thresholds and Set-Aside Tenders (2026)

CategoryWorkforce CapRevenue or Capital Limit
Micro Enterprise (Industry & Works)Up to 10 employeesVND 3 billion max revenue or capital
Small Enterprise (Industry & Works)Up to 100 employeesVND 50 billion max revenue or VND 20 billion capital
Set-Aside Civil Tenders (E-BDL 5.1)Domestic works <= VND 5BSimilar contract benchmark typically 50% (or 40% to 50%)

Checklist for SME Preferences and Proportionate Similar-Contract Criteria

  • Apply the SME set-aside flag in Section 5.1 E-BDL for domestic works packages valued at or below 5 billion VND.
  • Verify social-insurance headcount, revenue, and capital thresholds against prior-year financial statements under Article 5 of Decree 80/2021/ND-CP.
  • Keep similar-contract thresholds within 40% to 50% under Footnote (13) of Template 3A and omit sub-item stacking inside a building structure.
  • Accept two immediately lower-grade works each at 50% or higher value, or waive prior-contract criteria where permitted for simple packages.

Legal Basis & Regulatory Scope

Point e of Clause 1, Points a and dd of Clause 2, and Point d of Clause 3, Article 10 of Bidding Law 22/2023/QH15 (as amended by Law 90/2025/QH15); Clause 2 of Article 8 and Clause 2 of Article 26 of Decree 214/2025/ND-CP; Clause 4 of Article 35 and Chapter III Template 3A of Circular 79/2025/TT-BTC; and Article 5 of Decree 80/2021/ND-CP.

Filed under: E-HSMT & Budgeting #Micro and Small Enterprises #Bidding Preferences #Similar Contracts #E-HSMT