Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Clause 3, Article 44); Government Decree No. 214/2025/ND-CP dated 04/08/202.
- Key Benchmark: As the general rule under Clause 12, Article 26 of Decree No.
- Execution Control: Preserve written evidence of unjustified refusals or exclusive letters to support e-GP violation reporting under Clause 12, Article 26.
01Regulatory Context & Core Scope
Manufacturer sales authorizations long served as a major anti-competitive barrier in medical equipment, IT infrastructure, and industrial machinery tenders. Whenever a manufacturer or local representative granted an authorization letter to a single favored distributor, competing trading firms with solid capability were excluded from technical evaluation. To curtail that abuse, Clause 12, Article 26 of Decree No. 214/2025/ND-CP strictly regulates authorization requirements inside E-HSMTs.
02Qualification Benchmarks & Bidder Preferences
As the general rule under Clause 12, Article 26 of Decree No. 214/2025/ND-CP, an E-HSMT must not demand a manufacturer's sales license, distributor authorization, partnership certificate, warranty or technical-support commitment letter, or any equivalent document for ordinary commercial goods readily available on the market.
The sole permitted exception covers specialized, complex goods that intrinsically depend on direct long-term manufacturer accountability for post-sale obligations such as specialized warranty service, preventive maintenance, complex repairs, proprietary spare parts, and OEM technical engineering support. Before inserting this prerequisite into Chapters III and V, the investor and consultant must document technical justification establishing why each covered line item requires direct OEM backing.
03Independent Appraisal, Petitions & Audit Trails
Clause 12, Article 26 of Decree No. 214/2025/ND-CP also establishes direct accountability against abusive channel practices. Where a manufacturer, representative office, or master distributor arbitrarily refuses authorization, revokes an issued letter without cause, or restricts letters exclusively to select bidders to suppress competition, affected bidders and investors may report the conduct for public violation posting on the National e-Procurement System.
If evaluators later discover that an E-HSMT demanded manufacturer authorization for ordinary goods outside the specialized exception, they must rely on Clause 3, Article 44 of Law No. 22/2023/QH15, Clause 5, Article 26 of Circular No. 79/2025/TT-BTC, and Clause 1, Article 29 of Decree No. 214/2025/ND-CP to disregard that unlawful restriction when assessing E-HSDTs. Strict enforcement shields tenders from valid petitions and keeps market competition open.
Checklist for Manufacturer Authorization Requirements in E-HSMT
- Audit the procurement schedule to remove manufacturer authorizations and OEM warranty commitments for standard commercial items.
- Document clear technical justification demonstrating specialized complexity and mandatory OEM post-sale services whenever the exception is invoked.
- Accept equivalent authorization documents issued by authorized master distributors where permitted by the E-HSMT.
- Preserve written evidence of unjustified refusals or exclusive letters to support e-GP violation reporting under Clause 12, Article 26.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Clause 3, Article 44); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 12, Article 26 and Clause 1, Article 29); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025 (Clause 5, Article 26).