Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Articles 37 through 40); Government Decree No. 214/2025/ND-CP dated 04/08/2.
- Key Benchmark: When dividing a project into separate packages or dividing a package into multiple lots under Article 37 of Law No.
- Execution Control: Budget realistic durations for E-HSMT drafting, appraisal, bid preparation, and 5-day pre-closing publication if updated estimates stay within total investment.
01Regulatory Context & Core Scope
Entering the 2026 fiscal year, preparing and approving Contractor Selection Plans (KHLCNT) benefits from streamlined intermediate steps under the investor-level decentralization enacted by Law No. 90/2025/QH15 and Decree No. 214/2025/ND-CP. Expanded approval autonomy, however, places direct accountability on investors and consultants to lock down accurate funding descriptions, compliant package lotting, and realistic procurement calendars.
Regarding funding alignment under Articles 38 and 39 of Law on Procurement No. 22/2023/QH15, funding descriptions in the KHLCNT table must match verbatim the annual public-investment allocation or recurrent-budget assignment decision for 2026. For multi-year packages or blended central and local funding, the submission must clearly separate each capital source to prevent State Treasury coding blocks during disbursement.
02Core Regulatory Provisions & Conditions
When dividing a project into separate packages or dividing a package into multiple lots under Article 37 of Law No. 22/2023/QH15 alongside Articles 17 and 18 of Decree No. 214/2025/ND-CP, decisions must reflect technical synergy, implementation sequence, and market consultation.
Under Clause 1, Article 18 of Decree No. 214/2025/ND-CP, multi-lot packages must explicitly disclose the estimated value of each individual lot so small and mid-sized suppliers can bid on selected lots. Artificially splitting packages below competitive bidding thresholds to invoke direct contracting remains strictly illegal.
03Pricing Methodology & Cost Controls
Another vital budgeting provision sits in Clause 2, Article 140 of Decree No. 214/2025/ND-CP. When a subsequently approved package cost estimate exceeds the KHLCNT budget without breaching the project's total investment ceiling, that approved estimate automatically supersedes the KHLCNT package price without formal plan amendment, provided the updated estimate is published on e-GP at least 5 days before bid closing, or 3 days for commodities with volatile pricing.
Finally, setting tender duration and start-date fields on e-GP under Circular No. 79/2025/TT-BTC requires realistic allowances for drawing and estimate finalization, E-HSMT appraisal, statutory bid preparation periods, and first-ranked bidder document checks. Accurate Q1 2026 scheduling avoids repeated plan-amendment cycles ahead of mid-year capital disbursement milestones.
Checklist for Preparing Early-2026 Contractor Selection Plans
- Copy exact funding source names and 2026 budget ceilings verbatim from approved capital or recurrent budget decisions.
- State the estimated value of each individual lot in multi-lot packages under Clause 1, Article 18 of Decree No. 214/2025/ND-CP.
- Verify package boundaries against technical logic and schedule without artificially splitting tenders to evade open competition.
- Budget realistic durations for E-HSMT drafting, appraisal, bid preparation, and 5-day pre-closing publication if updated estimates stay within total investment.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Articles 37 through 40); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 17, 18, and Clause 2, Article 140); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025.