Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (Articles 11, 12, and Clause 4, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28).
- Key Benchmark: Using Article 28 clarification requests, the Procuring Entity should require written explanation and official OEM specification confirmation for the exact model quoted.
- Execution Control: Reject post-closing model swaps and check suspicious mistranslations for potential fraud under Article 16.
01Regulatory Context & Core Scope
Suppliers bidding imported medical, IT, or MEP equipment routinely upload original manufacturer catalogs and datasheets in English or foreign languages. Under Article 12 of Bidding Law 22/2023/QH15, domestic procurement requires Vietnamese documentation, while international tenders under Article 11 use English or bilingual Vietnamese and English.
02Core Regulatory Provisions & Conditions
Under Circular 06/2024/TT-BKHDT templates, foreign-language technical brochures submitted in domestic tenders must include Vietnamese translations, with bidders legally responsible for accuracy. Where a bidder attaches the genuine manufacturer catalog for the quoted model yet omits translations on secondary pages, the panel should request the missing translation under Article 28 of Decree 24/2024/ND-CP rather than disqualifying immediately.
A sharper conflict arises when a bidder's self-typed Vietnamese technical schedule claims compliance (such as 50 kVA capacity) while the attached manufacturer catalog shows lower ratings for that exact model. Whenever self-typed compliance tables contradict original OEM literature, the evaluation panel must verify performance against official manufacturer datasheets.
03Procedural Sequence & e-GP Execution
Using Article 28 clarification requests, the Procuring Entity should require written explanation and official OEM specification confirmation for the exact model quoted. Under Clause 3, Article 28, bidders cannot swap in a wholly different model post-closing to cure an uncompliant bid, unless OEM records prove an approved configurable option already covered inside the bid price.
Where a bidder deliberately mistranslates a foreign datasheet to disguise non-compliance as compliant, the discrepancy ceases to be an innocent clerical omission and implicates procurement fraud under Clause 4, Article 16 of Bidding Law 22/2023/QH15. Evaluation teams should always audit translations directly against source OEM text before scoring pass or escalating sanctions.
Foreign Catalog & Translation Audit Checklist
- Enforce language rules under Article 12 of Bidding Law 2023 (Vietnamese for domestic tenders).
- Request missing Vietnamese translations via Article 28 clarification when genuine foreign catalogs were timely uploaded.
- Cross-check every critical metric between bidder schedules and source OEM sheets, prioritizing OEM specs on conflicts.
- Reject post-closing model swaps and check suspicious mistranslations for potential fraud under Article 16.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (Articles 11, 12, and Clause 4, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28); Circular 06/2024/TT-BKHDT (Chapter I Instructions to Bidders on E-HSDT language).