How to Evaluate Key Personnel and Equipment Declared Simultaneously on Concurrent Active Contracts

How to Evaluate Key Personnel and Equipment Declared Simultaneously on Concurrent Active Contracts
Applying Clause 2, Article 27 of Decree 24/2024/ND-CP to grant one replacement window when declared staff or machinery overlap with another contract, while separating good-faith overlap from fraud.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (Clause 4, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Clause 2, Article 27).
  • Key Benchmark: Rather than disqualifying immediately, the panel must follow Clause 2, Article 27 of Decree 24/2024/ND-CP.
  • Execution Control: Deny replacement and disqualify immediately if verification uncovers forged credentials or sham mobilization records.

01Regulatory Context & Core Scope

Construction and specialized engineering firms frequently bid on multiple e-GP tenders concurrently, causing the same site commanders, project engineers, or heavy machinery to appear across parallel bids. Bidding law does not prohibit listing the same personnel or equipment across multiple pending bids prior to contract awards, since award outcomes and mobilization dates remain uncertain at bid closing.

02Procedural Sequence & e-GP Execution

However, if e-GP records or public contract disclosures reveal during evaluation that proposed key staff or primary machinery are already committed full-time to another active contract overlapping the current schedule, the bidder fails to prove effective mobilization availability. Rather than disqualifying immediately, the panel must follow Clause 2, Article 27 of Decree 24/2024/ND-CP.

Clause 2, Article 27 explicitly mandates that where key personnel (excluding E-design roles in EPC, EP, EC, or turnkey packages) or key equipment fail requirements or lack mobilization availability, expressly including overlapping commitments on another active contract, the Procuring Entity must grant the bidder exactly one replacement opportunity per position within a reasonable timeframe.

03Core Regulatory Provisions & Conditions

Panels should distinguish two e-GP overlap scenarios carefully: appearing in another pending E-HSDT that has not yet been awarded does not prove an active schedule conflict unless both contracts materialize concurrently; confirmed conflict exists only where an active contract or parallel award overlaps site mobilization windows.

If the replacement candidate or machine submitted during that single Clause 2 window still fails E-HSMT criteria or remains committed elsewhere without credible release proof, the bid fails evaluation. Conversely, if verification exposes fabricated employment or forged equipment leases, no replacement is permitted and the bid is rejected for fraud under Clause 4, Article 16 of Bidding Law 22/2023/QH15.

Personnel & Equipment Overlap Evaluation Checklist

  • Separate pending co-bids from actual mobilization overlaps on awarded active contracts.
  • Grant one formal replacement opportunity per overlapping key staff or machinery position under Clause 2, Article 27.
  • Set a reasonable replacement deadline (at least 3 business days) and audit replacement credentials thoroughly.
  • Deny replacement and disqualify immediately if verification uncovers forged credentials or sham mobilization records.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (Clause 4, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Clause 2, Article 27); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Form 3A).

Filed under: Bid Evaluation & Award #Resource Overlap #Clause 2 Art 27 Decree 24 #Staff Replacement #Key Personnel
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.