Controlling Key Personnel and Construction Equipment Criteria in E-HSMT to Prevent Competition Restrictions

Controlling Key Personnel and Construction Equipment Criteria in E-HSMT to Prevent Competition Restrictions
Identifying unlawful staffing and machinery criteria deemed void under Clauses 3 and 4, Article 44 of Bidding Law 2023 alongside Clause 5, Article 24 and Annex 8 of Circular 06/2024/TT-BKHDT.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (Clauses 3 and 4, Article 44); Decree 24/2024/ND-CP dated 27 February 2024 (Article 27).
  • Key Benchmark: Implementing that rule, Clause 5, Article 24 and Annex 8 of Circular 06/2024/TT-BKHDT enumerate prohibited restrictions on staffing and machinery.
  • Execution Control: Remove any requirement for live staff interviews or proprietary machinery brand specifications.

01Regulatory Context & Core Scope

Key personnel and construction machinery sections generate the largest share of pre-bid disputes on e-GP. Under Clause 3, Article 44 of Bidding Law 22/2023/QH15, E-HSMT clauses must never restrict bidder participation or grant unfair advantages; any non-compliant requirement is legally void under Clause 4, Article 44.

02Qualification Benchmarks & Bidder Preferences

Implementing that rule, Clause 5, Article 24 and Annex 8 of Circular 06/2024/TT-BKHDT enumerate prohibited restrictions on staffing and machinery. Common violations include forcing key personnel to maintain active social insurance contributions or permanent employment contracts at the bidder prior to closing, rather than permitting lawful mobilization commitments.

For primary construction equipment, an E-HSMT cannot demand outright ownership while rejecting lease agreements or third-party mobilization commitments. Requiring excessive equipment fleets disconnected from the actual schedule or naming proprietary equipment brands also breaches Annex 8 of Circular 06/2024/TT-BKHDT.

03Core Regulatory Provisions & Conditions

Annex 8 further prohibits setting key-personnel criteria for general trades, skilled laborers, or positions lacking statutory licensing rules, as well as summoning key personnel for live interviews during evaluation. Standard off-the-shelf goods packages without complex installation should not impose key-personnel barriers.

Before releasing an E-HSMT, drafting and appraisal units should audit every staffing and equipment table row against Annex 8 of Circular 06/2024/TT-BKHDT and match site-commander qualifications to the exact project grade. If a restrictive term is mistakenly published, Clause 5, Article 24 bars the evaluation panel from disqualifying bidders on that void clause.

Staffing & Equipment Anti-Restriction Checklist

  • Eliminate requirements for prior social insurance enrollment or permanent payroll status at bid closing.
  • Accept ownership titles, valid lease agreements, and binding mobilization commitments for key equipment.
  • Align site commander and engineering qualifications strictly to project grade and exclude unskilled labor roles.
  • Remove any requirement for live staff interviews or proprietary machinery brand specifications.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (Clauses 3 and 4, Article 44); Decree 24/2024/ND-CP dated 27 February 2024 (Article 27); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Clause 5, Article 24, and Annex 8).

Filed under: E-HSMT & Budgeting #Key Personnel #Key Equipment #Competition Restriction #Annex 8 Circular 06/2024