E-HSMT & Budgeting

Circular 09/2024/TT-BXD Effective 15 October 2024: Updating Construction Cost Norms in Tender Package Budgets

Circular 09/2024/TT-BXD Effective 15 October 2024: Updating Construction Cost Norms in Tender Package Budgets
Reviewing the five amended norm annexes on construction, installation, maintenance, materials, and consulting fees under Circular 09/2024/TT-BXD effective 15 October 2024 and transition rules under Decree 10/2021/ND-CP.

Key Takeaways

  • Governing Scope: Circular 09/2024/TT-BXD dated 30 August 2024 of the Ministry of Construction (Articles 1, 2, and 3, effective 15 October 2024); Circular 12/2021/TT-BXD dated 31 Augu.
  • Key Benchmark: For ongoing projects, Article 2 of Circular 09/2024/TT-BXD directs transition handling to Clause 8, Article 44 of Decree 10/2021/ND-CP on construction investment cost management.
  • Execution Control: Reconcile work item descriptions and units between approved estimates and the e-GP bill of quantities.

01Regulatory Context & Core Scope

Effective 15 October 2024, Circular 09/2024/TT-BXD issued on 30 August 2024 by the Ministry of Construction amends and supplements key construction cost norms previously established in Circular 12/2021/TT-BXD. Cost engineers and independent verifiers preparing tender package estimates should reconcile affected norm codes before approving package ceilings and issuing E-HSMT.

02Core Regulatory Provisions & Conditions

Under Article 1 of Circular 09/2024/TT-BXD, revisions span five annexes amending Circular 12/2021/TT-BXD: Annex I updates civil works norms (earthworks, piling, concrete, formwork, and structural steel), Annex II adds technological equipment installation norms, and Annex III revises repair and maintenance norms.

Beyond direct construction trades, Annex IV introduces material consumption norms for new building components, while Annex V adjusts percentage norms for project management and construction consulting fees, including feasibility studies, design, and supervision. Applying updated consulting percentages keeps advisory package budgets aligned with current statutory allowances.

03Effective Dates & Transitional Scope

For ongoing projects, Article 2 of Circular 09/2024/TT-BXD directs transition handling to Clause 8, Article 44 of Decree 10/2021/ND-CP on construction investment cost management. Project teams must verify prior appraisal dates, signed contract status, and Competent Person determinations before deciding whether to revise approved package estimates.

When setting tender budgets under Article 16 of Decree 24/2024/ND-CP from 15 October 2024 onward, estimation teams should verify that cost software loads the amended Circular 09/2024/TT-BXD norm tables rather than legacy 2021 defaults. Bill of quantities descriptions and measurement units on e-GP must also remain synchronized with the approved budget.

Checklist for Updating Budgets Under Circular 09/2024/TT-BXD

  • Cross-check BOQ items against Annexes I through IV of Circular 09/2024/TT-BXD for budgets submitted from 15 October 2024.
  • Verify revised project management and consulting fee percentages in Annex V before approving consulting tender ceilings.
  • Confirm transitional applicability for budgets approved before 15 October 2024 under Clause 8, Article 44 of Decree 10/2021/ND-CP.
  • Reconcile work item descriptions and units between approved estimates and the e-GP bill of quantities.

Legal Basis & Regulatory Scope

Circular 09/2024/TT-BXD dated 30 August 2024 of the Ministry of Construction (Articles 1, 2, and 3, effective 15 October 2024); Circular 12/2021/TT-BXD dated 31 August 2021; Decree 10/2021/ND-CP (Clause 8, Article 44); Decree 24/2024/ND-CP (Article 16).

Filed under: E-HSMT & Budgeting #Circular 09/2024/TT-BXD #Construction Norms #Package Budget #Circular 12/2021/TT-BXD
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.