Key Takeaways
- 70% to 130% Band: Any quote or item exceeding +30% or dropping below -30% of the first-pass mean can be excluded.
- Post-Filter Mean: Recalculating the average on remaining valid quotes aligns package budgets with market reality.
- Audit Shield: Full compliance with public e-GP posting insulates the Project Owner from unilateral vendor pricing misconduct.
01Outlier Filtering Mechanism Under Decree 349/2026/ND-CP
A core technical reform introduced by Decree 349/2026/ND-CP (amending Point d, Clause 2, Article 18 of Decree 214/2025/ND-CP) addresses distorted pricing: where more than 1 valid quotation is obtained, the Project Owner may take the arithmetic mean and exclude any quotation or line item exceeding or falling below 30% of that initial average.
02Two-Step Worked Example of the 30% Deviation Threshold
Consider a concrete numerical calculation. Suppose three compliant e-GP quotes arrive for an equipment lot at 100 million VND, 115 million VND, and 195 million VND. Step 1 computes the initial mean: `(100 + 115 + 195) / 3 = 136.67 million VND`. The `+-30%` tolerance corridor spans 95.67 million VND to 177.67 million VND. Because 195 million VND exceeds the 177.67 million VND ceiling, it is excluded, and Step 2 recalculates the final package benchmark as `(100 + 115) / 2 = 107.50 million VND`.
03Average Versus Lowest Quote and Safe Harbor Conditions
Cost engineers frequently ask whether selecting the lowest quote (100 million) is safer against state audits than using the filtered mean (107.50 million). Previously, defensive selection of the lowest quote often produced under-funded package budgets that triggered zero-bid open tenders. Under Decree 349/2026/ND-CP, taking the post-exclusion average is the explicitly endorsed statutory method reflecting true market value.
Crucially, the decree reinforces Project Owner legal protection: when the Project Owner publishes the Quotation Request transparently on e-GP, applies the 30% outlier filter consistently without collusion, and exercises due verification, it is shielded from vicarious liability if a vendor is later found to have submitted artificially inflated or anti-competitive quotes.
When filtering item-by-item rather than whole-quote totals, estimators should retain rejected quotes inside a transparent calculation appendix flagging exact percentage variances beyond `+-30%` so appraisers and auditors can verify every computation step.
Worked Two-Step Illustration of the >30% Quotation Outlier Rule
| Submitted Quote (Million VND) | Ratio vs Step-1 Mean (136.67M) | Decree 349 Decision |
|---|---|---|
| Quotation 1: 100.00M | 73.17% (inside 70% to 130% band) | Retained for Step-2 calculation |
| Quotation 2: 115.00M | 84.14% (inside 70% to 130% band) | Retained for Step-2 calculation |
| Quotation 3: 195.00M | 142.68% (exceeds 130% ceiling) | Excluded as pricing outlier |
| Approved Package Estimate | (100.00 + 115.00) / 2 = 107.50M | Submitted as package budget baseline |
Audit-Ready Checklist for the 30% Outlier Filter & Average Calculation
- Tabulate every timely, compliant e-GP quotation without omitting valid submissions prematurely.
- Compute the first-pass arithmetic mean and establish the 70%-to-130% acceptance band per package or line item.
- Flag and exclude quotes or line-item prices above 130% or below 70% of the initial mean.
- Recalculate the second-pass mean from the remaining valid pool to form the proposed package price.
- Attach the full Excel computation sheet and raw vendor quotes to preserve safe-harbor audit protection.
Legal Basis & Regulatory Scope
Point d, Clause 2, Article 18 of Decree 214/2025/ND-CP dated 4 August 2025 (amended by Decree 349/2026/ND-CP dated 9 September 2026).