Key Takeaways
- Single Quote Is Valid: Amended rules accept a minimum of 1 valid e-GP quote provided technical compliance and price reasonableness are checked.
- No Informal Paper Substitutes: Zero online submissions cannot be patched with unposted paper quotes for ordinary goods.
- 12-Month Contract Fallback: Switch cleanly to published 12-month similar award prices or an independent valuation certificate, archiving the zero-response log.
01Root Causes Behind Thin or Empty e-GP RFQ Responses
Since 9 September 2026, procurement offices frequently confront an unexpected result when the mandatory 3-working-day Request for Quotation window closes on e-GP: the portal displays only one submitted quotation or zero responses.
02Legal Validity of Receiving a Single e-GP Quotation
Where exactly one quotation arrives via e-GP, Point d, Clause 2, Article 18 of Decree 214/2025/ND-CP as amended by Decree 349/2026/ND-CP requires at least 1 valid quotation while encouraging multiple offers. Provided the Project Owner complied with public posting rules and verified technical conformity, vendor capacity, and market reasonableness, that single e-GP quotation is legally sufficient to establish the package estimate.
Conversely, when e-GP records zero quotations, the riskiest mistake is soliciting three stamped paper quotations offline via informal contacts and discarding the portal record. Bypassing electronic collection undermines mandatory transparency and exposes the budget dossier to audit disallowance.
03Three Compliant Fallbacks When Zero Quotes Are Submitted
Instead, procurement teams should select among three compliant remedies: (1) inspect whether overly narrow specifications or a tight 3-working-day window deterred suppliers and extend or re-post for 5 to 7 working days; (2) switch to alternative pricing bases under Clause 2, Article 18, such as awarded contract prices for similar goods or services within 12 months published on e-GP; or (3) commission a licensed valuation certificate or verified statutory price listing.
Every step, especially system screenshots or exported zero-response logs showing expiry without submissions, must be formally minuted and archived inside the approval dossier to protect the Project Owner during post-audit reviews.
Decision Table for e-GP Quotation Collection Outcomes
| Portal Outcome at Cutoff | Legal Sufficiency | Recommended Project Owner Action |
|---|---|---|
| 2 or more valid quotes | Standard compliance | Filter >30% outliers and compute mean package estimate |
| Exactly 1 valid quote | Meets statutory minimum | Verify specs, benchmark against market awards, and approve |
| 0 quotes (standard goods) | Insufficient quotation basis | Extend posting or switch to 12-month award prices or appraisal |
| 0 e-GP quotes (healthcare) | Email or hard copy permitted | Consolidate timely quotes submitted via authorized channels within 10 days |
Action Plan for Single-Quote or Zero-Quote e-GP Outcomes
- Export official e-GP system logs documenting exact vendor response counts upon cutoff.
- If 1 quote is received: cross-check specification match and unit rates against recent e-GP awards before approval.
- If 0 quotes are received: audit technical specs for undue restriction and extend or re-post with a wider window.
- If timeline is urgent: switch cleanly to 12-month similar awarded contract prices or a licensed valuation certificate.
- Archive the zero-response posting record alongside the replacement valuation evidence for future audit defense.
Legal Basis & Regulatory Scope
Clause 2, Article 18 of Decree 214/2025/ND-CP dated 4 August 2025 (amended by Decree 349/2026/ND-CP dated 9 September 2026); Article 16 of Bidding Law 22/2023/QH15.