Key Takeaways
- Governing Scope: Bidding Law 43/2013/QH13 (Article 22) and Decree 63/2014/ND-CP (Article 54, in force in 2023); Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 Janua.
- Key Benchmark: The first key change appears in Point m, Clause 1, Article 23 of Law 22/2023/QH15.
- Execution Control: Draft rigorous contract terms on pricing, schedules, and warranties when opting for simplified direct appointment.
01Regulatory Context & Core Scope
During 2023, direct appointment operates under Article 22 of Bidding Law 43/2013/QH13 and Article 54 of Decree 63/2014/ND-CP. However, Bidding Law 22/2023/QH15, passed on 23 June 2023 and taking effect on 1 January 2024, elevates primary direct-appointment cases and monetary thresholds directly into Article 23 to strengthen statutory clarity and accountability.
02Pricing Methodology & Cost Controls
The first key change appears in Point m, Clause 1, Article 23 of Law 22/2023/QH15. While Article 54 of Decree 63/2014/ND-CP sets VND 100 million for recurrent procurement, VND 500 million for consulting and non-consulting services, and VND 1 billion for goods, works, and mixed packages, Law 22/2023/QH15 differentiates VND 50 million to VND 100 million for recurrent budgets from investment-project limits of VND 500 million for consulting and VND 1 billion for non-consulting, goods, works, and mixed tenders.
The second change expands and sharpens specialized grounds under Article 23 of Law 22/2023/QH15, explicitly covering urgent epidemic-control supplies, utility relocation for site clearance, UXO clearance, national security or state-secret works, and proprietary technology or copyright compatibility where only one contractor can deliver.
03Core Regulatory Provisions & Conditions
Procedurally, Clause 2, Article 23 and Clause 2, Article 43 of Law 22/2023/QH15 empower Project Owners to use simplified direct appointment for small packages under Point m by sending a draft contract directly to a qualified contractor rather than preparing and appraising a formal Request for Proposals.
When drafting selection plans in late 2023 for packages launching in early 2024, advisory teams must separate recurrent budgets from investment projects accurately so Decree 63/2014/ND-CP thresholds are not misapplied after 1 January 2024.
Checklist Comparing 2023 and 2024 Direct Appointment Thresholds
- Classify funding cleanly between recurrent operating budgets and investment projects before applying Point m, Clause 1, Article 23 ceilings.
- Verify Clause 2, Article 22 conditions under Law 43/2013/QH13 for packages issued prior to 1 January 2024.
- Confirm packages are never artificially split to fall below direct-appointment financial thresholds.
- Draft rigorous contract terms on pricing, schedules, and warranties when opting for simplified direct appointment.
Legal Basis & Regulatory Scope
Bidding Law 43/2013/QH13 (Article 22) and Decree 63/2014/ND-CP (Article 54, in force in 2023); Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Articles 23 and 43).