Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Article 42); packages executed during 2023 remain governed by Bidding Law 43/2013/QH13.
- Key Benchmark: Confirm the package falls within one of the four authorized advance-bidding categories under Clause 2, Article 42.
- Execution Control: Obtain selection plan approval from the project-preparation agency head or designated Project Owner before publishing notices.
01Regulatory Context & Core Scope
Under Vietnam's traditional investment sequence, Project Owners could not release bidding dossiers until formal investment approval was signed, delaying site clearance, construction drawings, and long-lead equipment procurement. Bidding Law 22/2023/QH15, passed on 23 June 2023 and taking effect on 1 January 2024, establishes a clear advance bidding mechanism under Article 42.
02Core Regulatory Provisions & Conditions
Clause 2, Article 42 of Bidding Law 22/2023/QH15 identifies four eligible categories: goods packages with clearly defined scope and technical specifications; consulting, non-consulting, goods, and works packages serving compensation, site clearance, utility relocation, UXO clearance, planning, and resettlement; project management, technical design, construction drawing, and supervision consulting packages; and ODA or concessional-loan packages required by donors.
Prior to formal project investment approval or loan-agreement execution, Clause 1, Article 42 permits completing preparation, appraisal, and approval of the contractor selection plan; shortlisting; drafting, appraising, and approving bidding documents; evaluating bids; and identifying the winning bidder.
03Security Validity & Commitment Scope
The core risk-control boundary under Article 42 mandates that contract finalization and signing may only proceed after official project investment approval or international loan-agreement signing. E-HSMT documents for advance tenders must explicitly disclose this condition precedent so bidders factor bid validity and security durations appropriately.
Approval authority for advance-bidding selection plans rests with the head of the project-preparation agency or the designated Project Owner. Once Law 22/2023/QH15 enters into force in 2024, project management teams can run engineering design and site-clearance procurement concurrently with final project appraisal.
Checklist for Advance Bidding Under Article 42
- Confirm the package falls within one of the four authorized advance-bidding categories under Clause 2, Article 42.
- State clearly in the E-HSMT that contract finalization and signing depend on formal project approval or loan execution.
- Calibrate bid validity and bid security durations against projected investment sign-off dates to avoid repeated extensions.
- Obtain selection plan approval from the project-preparation agency head or designated Project Owner before publishing notices.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Article 42); packages executed during 2023 remain governed by Bidding Law 43/2013/QH13.