Key Takeaways
- Governing Scope: Law 57/2024/QH15 dated 29 November 2024 (Article 4, effective 15 January 2025); Bidding Law 22/2023/QH15.
- Key Benchmark: Under Article 4 of Law 57/2024/QH15, small-value direct contracting thresholds in Point m, Clause 1, Article 23 of Bidding Law 22/2023/QH15 are expanded.
- Execution Control: Update conflict-of-interest review templates under amended Article 6 for consultants and participating bidders.
01Regulatory Context & Core Scope
On 29 November 2024, the National Assembly passed Law 57/2024/QH15 amending selected provisions of the Planning Law, Investment Law, PPP Law, and Bidding Law. Taking effect on 15 January 2025, the statute removes practical implementation bottlenecks observed during the first year of Bidding Law 22/2023/QH15.
02Pricing Methodology & Cost Controls
Under Article 4 of Law 57/2024/QH15, small-value direct contracting thresholds in Point m, Clause 1, Article 23 of Bidding Law 22/2023/QH15 are expanded. For procurement budgets outside investment projects, the threshold rises from 100,000,000 VND to 300,000,000 VND; for investment projects, the ceilings remain 500,000,000 VND for consulting services and 1,000,000,000 VND for non-consulting, goods, works, and mixed packages.
Article 42 on advance tendering is also amended to broaden packages eligible for pre-approval tender preparation before project investment approval or international loan signing. Preparatory packages for site clearance, utility relocation, UXO clearance, resettlement, detailed engineering, and well-defined goods procurement can advance earlier to shorten project schedules.
03Security Validity & Commitment Scope
Law 57/2024/QH15 further revises Article 3 on concessional foreign loans, allowing lead negotiating agencies to submit donor-rule deviations to the Government rather than undergoing protracted legislative consultations. Amendments to Article 29 on special selection procedures and Article 6 on bidder independence clarify procurement handling for specialized science, technology, defense, and security assignments.
Between 30 November 2024 and 14 January 2025, active procurement procedures continue under Bidding Law 22/2023/QH15 and Decree 24/2024/ND-CP. Project owners and management boards should review their early-2025 procurement plan pipelines so updated thresholds and advance-tendering workflows align cleanly with the 15 January 2025 commencement date.
Preparation Steps Ahead of 15 January 2025
- Identify recurrent procurement packages up to 300,000,000 VND scheduled for release from 15 January 2025 onward.
- Screen site-clearance, engineering, and defined goods packages eligible for advance tendering under revised Article 42.
- Keep all submissions approved prior to 15 January 2025 compliant with unamended Bidding Law 22/2023/QH15 and Decree 24/2024/ND-CP.
- Update conflict-of-interest review templates under amended Article 6 for consultants and participating bidders.
Legal Basis & Regulatory Scope
Law 57/2024/QH15 dated 29 November 2024 (Article 4, effective 15 January 2025); Bidding Law 22/2023/QH15; Decree 24/2024/ND-CP dated 27 February 2024.