Policy & Procurement Law

Zero Bids or All Non-Responsive Submissions at Opening: Conditions for Switching to Direct Contracting Under Decree 349/2026/ND-CP

Zero Bids or All Non-Responsive Submissions at Opening: Conditions for Switching to Direct Contracting Under Decree 349/2026/ND-CP
Procedural guide under Point e1, Clause 2, Article 78 and Clause 4, Article 140 (Decree 349/2026/ND-CP) to pivot from failed open tenders to direct contracting without losing disbursement timelines.

Key Takeaways

  • Two Remedies at Zero-Bid Cutoff: Project Owners may either extend the deadline or convert directly to direct contracting under Point e1.
  • No Standard Relaxation: The nominated direct contractor must still pass full qualification and core technical criteria.
  • Plan Sequence: Complete formal cancellation (if opened) and KHLCNT method amendment prior to executing the direct award.

01Schedule Pressure When Competitive Tenders Yield No Winner

During peak public-investment disbursement periods, advertised open tenders or competitive quotations sometimes close with zero bids submitted, or evaluation reveals every E-HSDT fails technical or eligibility criteria. Re-advertising a full second tender cycle typically costs another 20 to 30 days, jeopardizing annual budget execution.

02Point e1 & Clause 4 Article 140 Direct-Contracting Remedy

To resolve this bottleneck, Decree 349/2026/ND-CP amended Clause 4, Article 140 and added Point e1, Clause 2, Article 78 of Decree 214/2025/ND-CP, enabling Project Owners to pivot cleanly to direct contracting where competitive tendering yields zero participants or zero responsive bids.

Executing the transition cleanly requires proper sequencing of the Contractor Selection Plan (KHLCNT). When converting from an unsuccessful or zero-bid competitive tender under Point e1, Clause 2, Article 78 (rather than simply extending the bid deadline), the Project Owner should formally cancel the failed round where required and record the plan amendment shifting the selection method to direct contracting before issuing the RFP.

03Anti-Relaxation & Budget Guardrails During Direct Award

Two strict safeguards remain binding during direct conversion: package value cannot be inflated without approved budget revision, and the nominated contractor must fully satisfy eligibility, experience, and core technical standards equivalent to the original competitive requirements.

Where zero bids stemmed from unduly restrictive E-HSMT criteria or severely under-estimated package budgets, Project Owners should first correct the defective specifications or cost estimate rather than carrying flawed parameters into direct contracting.

Decision Options After Zero-Bid Cutoff or Total Disqualification

Observed SituationOption 1: Extend / Re-TenderOption 2: Point e1 Direct Contracting
Zero bids submitted at closingExtend closing deadline on e-GPConvert under Point e1 after updating procurement plan
All submitted E-HSDTs fail criteriaCancel round, revise restrictive specs, re-bidCancel round and directly contract a fully qualified vendor
Typical turnaround timeApproximately 15 to 30 working daysApproximately 7 to 12 working days
Primary Governance FocusAvoiding annual capital disbursement delaysVerifying nominee capability and preserving budget ceiling

Five-Step Protocol for Zero-Bid Conversion to Direct Contracting

  • Export the zero-bid opening record or Form 02A evaluation report confirming all submissions failed compliance.
  • Audit whether tender failure resulted from outdated budgets or inadvertently restrictive E-HSMT thresholds.
  • Issue a formal cancellation decision (where failed bids were opened) and publish it promptly on e-GP.
  • Approve the procurement-plan method amendment converting the package to direct contracting under Point e1, Clause 2, Article 78.
  • Issue the RFP and verify the selected contractor's full capability without relaxing core quality standards.

Legal Basis & Regulatory Scope

Point e1, Clause 2, Article 78 and Clause 4, Article 140 of Decree 214/2025/ND-CP (amended by Decree 349/2026/ND-CP dated 9 September 2026); Article 17 of Bidding Law 22/2023/QH15.

Filed under: Policy & Procurement Law #Zero Bids Received #Point e1 Clause 2 Art. 78 #Direct Contracting Fallback #Decree 349/2026
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.