Policy & Procurement Law

Executing Contractor Selection in Early 2024 as Bidding Law 22/2023/QH15 Takes Effect

Executing Contractor Selection in Early 2024 as Bidding Law 22/2023/QH15 Takes Effect
Guidance on handling transitional tenders under Article 96, adjusting selection plans with unissued E-HSMTs, and applying self-executing provisions of Law 22/2023/QH15 from 1 January 2024.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Articles 5, 14, 16, 23, 95, and 96); transitional application for packages issued prior to 1 January 2024 under Law 43/2.
  • Key Benchmark: Verify actual e-GP publication dates to separate legacy tenders under Law 43/2013/QH13 from packages governed by Law 22/2023/QH15.
  • Execution Control: Archive e-GP publication timestamps prior to 1 January 2024 to substantiate transitional eligibility under Article 96.

01Regulatory Context & Core Scope

On 1 January 2024, Bidding Law 22/2023/QH15 officially took effect under Article 95, replacing Bidding Law 43/2013/QH13. During the opening weeks of 2024, while detailed implementing decrees and circulars remain under final review, Project Owners and Management Units must classify every active package precisely to avoid procurement bottlenecks.

02Procedural Sequence & e-GP Execution

The first category comprises tenders whose invitations, prequalification documents, bidding dossiers, or requests for proposals were already approved and issued prior to 1 January 2024. Under Clause 1, Article 96 of Bidding Law 22/2023/QH15, these legacy packages continue through opening, evaluation, contract signing, and contract administration under the prior framework of Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT.

The second category involves packages with selection plans approved before 1 January 2024 whose E-HSMT or HSYC has not yet been issued. Project Owners must audit contractor selection methods, direct-appointment ceilings, preparation timelines, and preference rules against Law 22/2023/QH15; any conflicting plan elements must be formally amended before publishing tender notices.

03Security Validity & Commitment Scope

For brand-new packages initiated in early 2024, Project Owners apply self-executing rules embedded directly in Law 22/2023/QH15, including bidder eligibility under Article 5, the nine prohibited conduct groups under Article 16, statutory direct-appointment limits under Point m, Clause 1, Article 23, and the shortened 14-day bid-security release deadline under Article 14.

In early January 2024 engagements, VNTender advises documenting the exact e-GP notice publication timestamp as the controlling legal boundary and sequencing non-urgent releases whose detailed thresholds depend on forthcoming implementing regulations.

Early-2024 Tender Transition Checklist

  • Verify actual e-GP publication dates to separate legacy tenders under Law 43/2013/QH13 from packages governed by Law 22/2023/QH15.
  • Audit 2023-approved selection plans with unissued E-HSMTs and amend any methods or thresholds inconsistent with Law 22/2023/QH15.
  • Incorporate Article 23 direct-appointment ceilings, Article 5 household business eligibility, and 14-day security release rules into new dossiers.
  • Archive e-GP publication timestamps prior to 1 January 2024 to substantiate transitional eligibility under Article 96.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 dated 23 June 2023 (Articles 5, 14, 16, 23, 95, and 96); transitional application for packages issued prior to 1 January 2024 under Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT.

Filed under: Policy & Procurement Law #Bidding Law 2023 #Effective Jan 2024 #Tender Transition #Selection Plan
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.