Key Takeaways
- Governing Scope: Bidding Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT (currently active in 2023); Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect.
- Key Benchmark: Clause 3, Article 96 further governs transitional coordination for land-using investment projects pending amended land legislation.
- Execution Control: Archive official e-GP publication receipts as audit evidence supporting transitional applicability under Article 96.
01Regulatory Context & Core Scope
As 1 January 2024 approaches, project management teams face a pivotal compliance question: whether tenders approved in November and December 2023 remain governed by Law 43/2013/QH13 or must shift to Bidding Law 22/2023/QH15. The answer rests on Article 96 of Law 22/2023/QH15, already passed by the National Assembly and scheduled to take effect on 1 January 2024.
02Core Regulatory Provisions & Conditions
Clause 1, Article 96 of Bidding Law 22/2023/QH15 sets a strict dual condition: only packages whose prequalification, expression-of-interest, bidding documents, or RFP dossiers have been both approved and actually issued prior to 1 January 2024 may continue selection, contracting, and administration under Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT.
A common pitfall arises when an approval decision is signed in late December 2023, yet the procuring entity fails to publish the E-HSMT on e-GP before midnight on 31 December 2023. Because the issuance condition is unmet, that unissued dossier must be revised to match Law 22/2023/QH15 before release in 2024.
03Effective Dates & Transitional Scope
Clause 2, Article 96 establishes the same dual rule for investor selection in business investment projects: both approval and dossier issuance before 1 January 2024 are required to remain under Law 43/2013/QH13. Clause 3, Article 96 further governs transitional coordination for land-using investment projects pending amended land legislation.
In Q4 2023 advisory engagements, VNTender recommends maintaining a cutover tracker for every package approved late in the year. If engineering design or budget reviews prevent reliable e-GP publication before 25 December 2023, owners should plan directly for the 2024 statutory framework rather than duplicating appraisal effort.
Checklist for Late-2023 Transitional Package Classification
- Track both approval signature dates and actual e-GP publication timestamps prior to 1 January 2024.
- Prioritize appraisal and early release before the final week of December 2023 for dossiers prepared under Circular 08/2022/TT-BKHDT.
- Flag any approved packages unlikely to release within 2023 so they can be aligned cleanly with Law 22/2023/QH15.
- Archive official e-GP publication receipts as audit evidence supporting transitional applicability under Article 96.
Legal Basis & Regulatory Scope
Bidding Law 43/2013/QH13, Decree 63/2014/ND-CP, and Circular 08/2022/TT-BKHDT (currently active in 2023); Bidding Law 22/2023/QH15 passed 23 June 2023, taking effect on 1 January 2024 (Article 96).