Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (Clauses 4 and 8, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28).
- Key Benchmark: To resolve such cases fairly, panels must distinguish statutory liability under Clause 8, Article 16 of Bidding Law 22/2023/QH15.
- Execution Control: Reject immediately and escalate sanctions if verification reveals sham paper contracts or forged documentation.
01Regulatory Context & Core Scope
Under Chapter III of E-HSMT templates issued with Circular 06/2024/TT-BKHDT, bidders may submit past contracts executed as sole prime contractor, joint venture partner, management contractor, or subcontractor to satisfy similar-experience criteria. Disputes frequently arise when evaluation panels discover that a submitted subcontract lacked written owner approval under the prior prime contract or exceeded that prime contract's maximum subcontracting cap.
02Qualification Benchmarks & Bidder Preferences
To resolve such cases fairly, panels must distinguish statutory liability under Clause 8, Article 16 of Bidding Law 22/2023/QH15. The legal prohibition against unauthorized assignment or unapproved subcontracting binds the prime contractor that signed the original contract with that former Project Owner, without automatically erasing technical capability actually executed on site by the subcontractor.
Capacity evaluation under Article 27 of Decree 24/2024/ND-CP focuses on whether the current bidder genuinely performed work of comparable scale and technical nature. Where the subcontractor provides a complete evidentiary trail (signed subcontract, accepted quantity completion minutes, site handover records, and tax-verified VAT invoices matching declared revenue), panels should not automatically disqualify the experience solely because the former prime contractor failed to secure internal owner sign-off.
03Contract Performance, Settlement & Amendments
Conversely, two scenarios mandate non-recognition: where a competent authority declared the prior subcontract void or uncovered paper-only invoicing without actual site execution, and where attached acceptance sheets or invoices prove forged or fabricated under Clause 4, Article 16 of Bidding Law 22/2023/QH15.
Given these nuances, Procuring Entities should apply Clauses 1 and 5 of Article 28 of Decree 24/2024/ND-CP to seek detailed clarification and cross-verify electronic invoices and acceptance records directly with the former Project Owner or prime contractor. Documenting physical execution proof clearly inside the evaluation report keeps award decisions defensible during appraisal and audit.
Subcontract Similar-Experience Verification Checklist
- Verify complete execution proof: signed subcontract, quantity acceptance minutes, and valid VAT invoices.
- Separate the former prime contractor's Clause 8, Article 16 assignment breach from the subcontractor's actual field execution.
- Issue Article 28 clarifications and verify electronic invoices and acceptance logs with former project counterparties.
- Reject immediately and escalate sanctions if verification reveals sham paper contracts or forged documentation.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (Clauses 4 and 8, Article 16); Decree 24/2024/ND-CP dated 27 February 2024 (Articles 27 and 28); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Form 3A).