Bid Evaluation & Award

Handling Bid Securities Effective Later Than the Bid Closing Timestamp on e-GP

Handling Bid Securities Effective Later Than the Bid Closing Timestamp on e-GP
Analyzing bid guarantees whose effective timestamp starts after the e-GP closing deadline: why Article 14 of Law 22/2023/QH15 and Article 30 of Decree 24/2024/ND-CP require automatic rejection without cure.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 14); Government Decree 24/2024/ND-CP dated 27 February 2024 (Articles 28 and 30).
  • Key Benchmark: Verify the exact final closing date and hour on the latest e-TBMT notice, including any E-HSMT addenda.
  • Execution Control: Record exact timestamp discrepancies in the validity evaluation schedule whenever a bid security fails compliance.

01Regulatory Context & Core Scope

During electronic bid openings on the National e-Procurement System, otherwise competitive bidders frequently face disqualification due to a single line stating the start time of bid security validity. A common scenario occurs when e-GP closes bidding at 08:00 AM, whereas the issuing bank writes that the guarantee takes effect at 09:00 AM on the same day or on the next calendar date.

02Security Validity & Commitment Scope

Under Clause 4, Article 14 of Bidding Law 22/2023/QH15 and Point d, Clause 2, Article 30 of Decree 24/2024/ND-CP, bid security must satisfy the exact value and validity duration required by the E-HSMT continuously from the bid submission deadline. Even a one-hour coverage gap leaves the Project Owner unprotected if a bidder withdraws immediately after opening.

Upon detecting this defect during validity screening, the Bid Evaluation Panel cannot ask the bidder to clarify or submit a post-closing bank amendment retrofitting the start timestamp. Under Article 28 of Decree 24/2024/ND-CP and Circular 01/2024/TT-BKHDT standard forms, continuous validity from bid closing is a strict mandatory condition; any security beginning later or expiring earlier is non-responsive and requires rejection.

03Procedural Sequence & e-GP Execution

In practice, such gaps arise when commercial bank branches stamp standard business opening hours or when an E-HSMT addendum shifts the closing hour earlier in the day. Because electronic bid guarantees on e-GP bind structured timestamps directly from issuing banks, contractors must inspect exact hour fields before submitting their bids.

To avoid fatal errors, Hoang Quan Construction Development Investment Consulting Co., Ltd. (VNTender) advises bidders to instruct banks to set guarantee commencement from the issuance date or at least one full day prior to closing. For evaluation panels, documenting the exact bank start timestamp alongside the e-GP opening record ensures an airtight, indisputable validity ruling.

Checklist for Bid Security Effective Timestamp Verification

  • Verify the exact final closing date and hour on the latest e-TBMT notice, including any E-HSMT addenda.
  • Confirm the guarantee start timestamp on electronic or scanned bank letters is no later than the bid closing time.
  • Count continuous validity days from the closing date through the full minimum period required in the Bid Data Sheet.
  • Record exact timestamp discrepancies in the validity evaluation schedule whenever a bid security fails compliance.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 14); Government Decree 24/2024/ND-CP dated 27 February 2024 (Articles 28 and 30); Circular 01/2024/TT-BKHDT dated 15 February 2024.

Filed under: Bid Evaluation & Award #Bid Security #Bid Closing Time #Bid Validity #e-GP Platform
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.