Auditing Contract Negotiation and Joint-Liability Clauses in Bid Securities for Tenders Published From 9 September 2026

Auditing Contract Negotiation and Joint-Liability Clauses in Bid Securities for Tenders Published From 9 September 2026
Clause-by-clause audit method for Clause 5 (contract negotiation) and Clause 8 (joint-venture liability) in amended Forms 04A and 04B under Circular 134/2026/TT-BTC.

Key Takeaways

  • Governing Scope: Point d, Clause 3, Article 26 and Article 20 of Decree 214/2025/ND-CP; Circular 79/2025/TT-BTC (Article 27 and Forms 04A, 04B).
  • Key Benchmark: Evaluators must first verify the full clause count: 7 default undertakings for single bidders (Form 04A) and 8 for joint ventures (Form 04B).
  • Execution Control: Cross-check beneficiary details, exact E-TBMT guarantee value, validity from bid closing date, and post-release issuance date.

01Regulatory Context & Core Scope

From 9 September 2026 onward, E-HSMT tenders published under Models 3A through 12B of Circular 79/2025/TT-BTC became governed by Points a and b, Clause 3, Article 6 of Circular 134/2026/TT-BTC amending Bid Security Form 04A (single bidder) and Form 04B (joint venture). Early evaluations following the effective date showed banks repeatedly issuing legacy guarantee templates missing newly mandated default clauses, resulting in bid rejections.

02Qualification Benchmarks & Bidder Preferences

Evaluators must first verify the full clause count: 7 default undertakings for single bidders (Form 04A) and 8 for joint ventures (Form 04B). The pivotal addition is Clause 5, committing the guarantor to pay if the bidder fails or refuses to attend contract negotiation within 5 working days of invitation or refuses to sign negotiation minutes, excluding force majeure.

Reviewers should simultaneously confirm exact wording for the other statutory timelines: 5 working days for document verification (Clause 4), 10 days for contract finalization from award notice unless exempted under Clause 4, Article 34 of Decree 214/2025/ND-CP (Clause 6), and 10 days for contract signing after finalization (Clause 7). Under Footnotes (4) and (5), omitting any required clause constitutes an adverse condition under Clause 18.3 E-CDNT and renders the bid security invalid.

03Security Validity & Commitment Scope

For joint ventures submitting Form 04B, panels must verify Clause 8 on joint forfeiture: if any partner triggers forfeiture under Clause 18.5 E-CDNT, the bid security of all consortium members is forfeited. Where partners issue separate guarantees per Footnote (2), every guarantee must retain all 8 clauses and use the same submission format—either all electronic guarantees or all scanned paper guarantees under Point a, Clause 1, Article 27 of Circular 79/2025/TT-BTC.

Finally, verify beneficiary accuracy against Clause 1.1 E-BDL, issuance dated after E-HSMT release, secured value meeting the e-GP notice requirement (including triple security under Article 20 of Decree 214/2025/ND-CP where applicable), validity days counted from the bid closing date, and valid execution by an authorized guarantor officer.

Audit Checkpoints for Bid Security From 9 September 2026

  • Verify all 7 clauses (single bidder) or 8 clauses (joint venture) required under Clause 3, Article 6 of Circular 134/2026/TT-BTC.
  • Confirm Clause 5 on contract negotiation within 5 working days has not been omitted due to legacy bank templates.
  • Verify Clause 8 joint-venture forfeiture language and consistent e-guarantee or paper format across all consortium members.
  • Cross-check beneficiary details, exact E-TBMT guarantee value, validity from bid closing date, and post-release issuance date.

Legal Basis & Regulatory Scope

Point d, Clause 3, Article 26 and Article 20 of Decree 214/2025/ND-CP; Circular 79/2025/TT-BTC (Article 27 and Forms 04A, 04B); Points a and b, Clause 3, Article 6 of Circular 134/2026/TT-BTC dated 9 September 2026.

Filed under: Bid Evaluation & Award #Bid Security #Circular 134/2026 #Circular 79/2025 #E-HSDT