Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 29 and 30).
- Key Benchmark: 70/2025/ND-CP effective 01/06/2025) and Ministry of Finance Circular No.
- Execution Control: Inspect any adjustment or replacement invoices under Circular No. 32/2025/TT-BTC so revenue values are never double-counted.
01Regulatory Context & Core Scope
When verifying similar completed contracts inside an E-HSDT, inspecting the signed contract alone proves only initial intent rather than actual completion. Evaluation panels must cross-check the contract, quantity schedules, commissioning handover certificates, and corresponding electronic VAT invoices together.
02Effective Dates & Transitional Scope
Under Decree No. 214/2025/ND-CP and Circular No. 79/2025/TT-BTC, completion of a reference contract is anchored to the formal acceptance and handover date. For construction works, the commissioning certificate placing the facility into service under Decree No. 06/2021/ND-CP must carry signatures and seals from the investor, supervision consultant, and contractor; interim milestone certificates do not prove full project completion unless the E-HSMT expressly credits completed independent components.
Inspecting electronic VAT invoices independently verifies real project revenue and execution. Under Clause 2, Article 9 of Decree No. 123/2020/ND-CP (as amended by Decree No. 70/2025/ND-CP effective 01/06/2025) and Ministry of Finance Circular No. 32/2025/TT-BTC replacing Circular No. 78/2021/TT-BTC, the statutory issuance timestamp for construction and services is the date of completion acceptance regardless of whether cash settlement has occurred.
03Pricing Methodology & Cost Controls
When reviewing scanned VAT invoices in an E-HSDT, panels should verify the tax authority code, invoice series, serial number, and lookup code directly on the General Department of Taxation electronic invoice portal. Because Circular No. 32/2025/TT-BTC abolished cancellation of issued electronic invoices from 01/06/2025 in favor of adjustment or replacement invoices, any invoice showing an adjusted, replaced, or legacy cancelled status without a valid replacement invoice cannot support contract value recognition.
Where acceptance dates diverge sharply from digital invoice timestamps, or project titles and buyer tax IDs mismatch the reference contract, panels must issue an Article 30 clarification request under Decree No. 214/2025/ND-CP and inspect original electronic invoices and bank transfer proofs during document verification.
Verification Checklist for e-Invoices and Handover Minutes
- Verify that commissioning and handover certificates carry authorized signatures and seals from the investor, supervisor, and contractor.
- Validate electronic invoice codes directly on the tax authority's official lookup portal to confirm active validity.
- Cross-check invoice issuance dates against acceptance dates, project descriptions, accepted amounts, and buyer tax IDs.
- Inspect any adjustment or replacement invoices under Circular No. 32/2025/TT-BTC so revenue values are never double-counted.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 29 and 30); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025; Government Decree No. 123/2020/ND-CP dated 19/10/2020 (as amended by Decree No. 70/2025/ND-CP dated 20/03/2025) and Ministry of Finance Circular No. 32/2025/TT-BTC dated 31/05/2025; Government Decree No. 06/2021/ND-CP dated 26/01/2021.