Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 2, Article 29.
- Key Benchmark: If any declared machine fails capacity specs, carries an expired inspection, or lacks supporting ownership or lease documents, Article 30 of Decree No.
- Execution Control: Administer equipment clarification or replacement up to two times per position with at least 3 working days per round.
01Regulatory Context & Core Scope
Under Clause 2, Article 29 of Decree No. 214/2025/ND-CP and Circular No. 79/2025/TT-BTC forms, domestic works evaluations initially assess major construction equipment based on the bidder's commitment inside the bid submission form. Full documentary verification against Form 06D declarations is conducted strictly for the first-ranked bidder, shortening review time across lower-ranked bids.
02Qualification Benchmarks & Bidder Preferences
For bidder-owned equipment, panels must verify purchase invoices, sales contracts, specialized vehicle registrations, or lawful ownership proofs matching the exact license plate, chassis number, engine number, and rated capacity or load specified in the E-HSMT. Where equipment falls under statutory occupational-safety inspection rules, such as cranes, hoists, or rollers, valid safety inspection certificates must also be verified.
For leased equipment, a strict verification discipline applies: never extrapolate lessor identities across separate machines. Seeing one excavator leased from lessor A does not justify assuming dump trucks or bulldozers share the same lessor. Evaluators must inspect each individual principle lease agreement for lessor name, contract reference, signing date, quantity, and capacity, and open each corresponding registration or inspection scan to confirm exact plate numbers and expiry dates.
03Procedural Sequence & e-GP Execution
If any declared machine fails capacity specs, carries an expired inspection, or lacks supporting ownership or lease documents, Article 30 of Decree No. 214/2025/ND-CP permits clarification, supplementation, or replacement. Each replacement round must allow at least 3 working days, capped at a maximum of two replacements per equipment position before disqualification applies.
Finally, evaluators must carefully distinguish the minimum major-equipment table in Chapter III of the E-HSMT from peak-mobilization equipment schedules inside technical methodology proposals. Only Chapter III mandatory minimums govern capability pass-or-fail compliance, and panels must never invent unstated age limits or extra supporting papers outside approved E-HSMT criteria.
Verification Checklist for Key Construction Equipment
- Perform full equipment document checks for the first-ranked bidder based on Form 06D entries on e-GP.
- Inspect each principle lease agreement, vehicle registration, and safety inspection certificate individually without cross-machine assumptions.
- Reconcile rated capacity, load limits, and inspection validity on scanned originals directly against Chapter III E-HSMT requirements.
- Administer equipment clarification or replacement up to two times per position with at least 3 working days per round.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 2, Article 29; Clauses 1 and 2, Article 30); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 (Form 06D and works E-HSMT forms) and No. 80/2025/TT-BTC dated 08/08/2025.