Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Arti.
- Key Benchmark: Complete arithmetic correction, deviation adjustment, and discount deduction under Article 31 of Decree No. 214/2025/ND-CP before declaring an overrun.
- Execution Control: Archive signed negotiation minutes, revised price offers, and plan amendment approvals whenever the package ceiling is adjusted.
01Regulatory Context & Core Scope
When e-GP bid-opening readouts show quoted prices above the approved package budget, many investors prematurely move to cancel the tender and revise cost estimates. Jumping directly to cancellation wastes weeks of procurement schedule and bypasses mandatory arithmetic checks, because the unadjusted opening price is never the legal figure used to establish a budget overrun.
02Pricing Methodology & Cost Controls
Under Article 31 of Decree No. 214/2025/ND-CP, the evaluation panel must complete arithmetic error correction, reconcile unit-price versus total mismatches, check figures against words, adjust scope deviations, and deduct valid unconditional discounts. Only the resulting post-correction, post-adjustment net bid price provides the lawful benchmark against the approved package budget.
Where every technically compliant ranked bidder exceeds the approved package budget after error correction, deviation adjustment, and discount deduction, the investor selects one or a combination of remedies under Clause 8, Article 140 of Decree No. 214/2025/ND-CP. First, if the original package price fully reflects execution cost components, the investor may invite those bidders to submit revised price offers within a preparation window not exceeding 10 days.
03Contract Performance, Settlement & Amendments
Alternatively, the investor may permit price re-bidding alongside reviewing the package budget or E-HSMT terms where costing norms appear outdated; if adjusting the package budget in the contractor selection plan is required, approval must conclude within 10 days of request receipt. The investor may also conduct a simplified online quotation among eligible bidders or, in open bidding, invite the first-ranked bidder to price negotiations capped below the lowest post-correction, post-adjustment offer.
Inside the evaluation report prepared under Circular No. 80/2025/TT-BTC, panels should document itemized arithmetic corrections, deviation percentages, and a formal situation-handling proposal prior to initiating negotiation or price re-submission. Following those structured statutory steps preserves auditability while avoiding unnecessary re-tendering delays.
Checklist for Handling Corrected Bids Exceeding Package Budgets
- Complete arithmetic correction, deviation adjustment, and discount deduction under Article 31 of Decree No. 214/2025/ND-CP before declaring an overrun.
- Verify whether only the top-ranked bid or every technically responsive bid exceeds the approved budget.
- Apply an appropriate remedy under Clause 8, Article 140 of Decree No. 214/2025/ND-CP, such as 10-day re-bidding, simplified online quotation, or price negotiation.
- Archive signed negotiation minutes, revised price offers, and plan amendment approvals whenever the package ceiling is adjusted.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Article 31; Clauses 2 and 8, Article 140); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.