Key Takeaways
- No Automatic Rejection: Bids under 80% require formal written clarification before any rejection decision.
- Evidence-Based Acceptance: Accept explanations only when backed by verifiable supplier pricing or owned machinery economies.
- Up to 30% Bond: Competent Person approval enables elevating performance security up to 30% to deter default.
01The 80% Threshold for Works and EC Packages
Deeply discounted construction bids dropping 25% to 35% below approved budgets continue to challenge Project Owners, heightening risks of contractor abandonment or substandard material substitution. Under Article 140 of Decree 214/2025/ND-CP (as amended by Decree 349/2026/ND-CP), evaluated works and EC bids falling below 80% of the approved package price trigger mandatory abnormally-low-bid scrutiny.
02Unit-Cost Clarification & Disqualification Standards
First, evaluation panels may never disqualify solely for crossing below 80%; they must issue a formal e-GP clarification request giving the bidder a defined window to substantiate price feasibility via unit-cost breakdowns, owned equipment deployment, bulk supplier contracts, or verifiable quarry proximity.
Second, evaluators benchmark the explanation against engineering norms and submitted documentation. Where unit rates fall inexplicably below production cost without credible inventory backing or commercial explanation, the Project Owner may reject the E-HSDT as unsubstantiated.
03Securing Approval for up to 30% Performance Security
Third, even if the low-price explanation proves credible and the bidder wins recommendation for award, the Project Owner can deploy enhanced default protection by raising the performance security above the standard 10% ceiling up to 30% of contract value pursuant to Clause 3, Article 68 of Bidding Law 22/2023/QH15.
Crucially, elevating performance security up to 30% requires explicit authorization inside the E-HSMT or written approval from the Competent Person so banks and contracting parties have an indisputable legal basis upon bond issuance.
Decision Outcomes for Bids Falling Under 80% of Package Budget
| Clarification Assessment | Evaluation Outcome | Performance Security Action |
|---|---|---|
| Generic assertions lacking cost evidence | Reject E-HSDT as unfeasible | Proceed to next ranked responsive bidder |
| Artificially omitted items (goods packages) | Apply missing-item deviation adjustment | Screen against mandatory 10% deviation ceiling |
| Credible owned-resource pricing, low default risk | Recommend for contract award | Standard 2% to 10% performance bond |
| Feasible but ultra-thin cost margin | Recommend award with elevated security | Request Competent Person sign-off up to 30% bond |
Checklist for Abnormally Low Works Bids (<80% of Package Budget)
- Compute ratio cleanly: divide bid price after arithmetic correction, deviation adjustment, and discount by approved package price.
- Issue an e-GP clarification asking for granular unit-rate breakdowns across key materials, labor, and plant.
- Verify attached evidence (binding supplier agreements, existing inventory invoices, haul-distance proofs) rather than generic statements.
- If unconvincing: document specific unfeasible unit items inside Form 02A before disqualifying.
- If recommending award: secure written Competent Person approval to elevate performance security up to 30%.
Legal Basis & Regulatory Scope
Clause 3, Article 68 of Bidding Law 22/2023/QH15; Article 140 of Decree 214/2025/ND-CP (amended by Decree 349/2026/ND-CP); Form 02A of Circular 134/2026/TT-BTC.