Technical Evaluation Under Scoring Versus Pass or Fail Methods in Goods Procurement

Technical Evaluation Under Scoring Versus Pass or Fail Methods in Goods Procurement
Comparing technical scoring (minimum 70% threshold) against pass-or-fail criteria for goods packages under Article 58 of the Procurement Law and Clause 4 Article 26 of Decree 214/2025/ND-CP.

Key Takeaways

  • Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Article 58); Government Decree No. 214/2025/ND-CP dated 04/.
  • Key Benchmark: A mandatory rule under Clause 4, Article 26 of Decree No.
  • Execution Control: Anchor every point tier to measurable thresholds verifiable against catalogs, factory datasheets, and quality certificates.

01Regulatory Context & Core Scope

Choosing incorrectly between pass-or-fail criteria and weighted technical scoring in goods tenders often distorts bidder rankings or creates defensibility gaps during independent appraisal. Article 58 of Law on Procurement No. 22/2023/QH15 together with Decree No. 214/2025/ND-CP defines clear boundaries, scoring scales, and minimum pass floors for both evaluation mechanisms.

02Qualification Benchmarks & Bidder Preferences

The pass-or-fail method fits standardized, commercially available goods evaluated under lowest-price or evaluated-price award rules. Every critical technical parameter, including capacity, construction materials, factory certifications, warranty duration, and delivery lead time, must be written as a verifiable quantitative threshold. A bid passes technical evaluation only when every general criterion and mandatory sub-criterion achieves a passing rating.

Technical scoring applies to packages involving complex equipment, multi-component system integration, or combined quality-and-cost evaluation. Under Clause 4, Article 26 of Decree No. 214/2025/ND-CP, technical criteria use a 100-point or 1,000-point scale with a minimum overall technical threshold of at least 70% of maximum technical points, raised to between 80% and 90% for packages carrying high technical complexity.

03Validity Boundaries & Common Evaluation Pitfalls

A mandatory rule under Clause 4, Article 26 of Decree No. 214/2025/ND-CP frequently breached in draft E-HSMTs governs sub-criterion minimums. While drafters may impose minimum scores on general criteria and core technical sub-criteria, setting minimum pass thresholds on non-core detail sub-criteria is strictly prohibited. Scoring rubrics must also anchor each point tier to objective specifications rather than vague labels such as good, fair, or average.

During bid evaluation using Circular No. 80/2025/TT-BTC and Circular No. 79/2025/TT-BTC templates, evaluation panels must score strictly against submitted technical datasheets, catalogs, and test certificates without inventing unstated sub-rubrics. Where competing products offer narrow technical differentiation but significant price spreads, opting for pass-or-fail criteria paired with evaluated price captures operating and maintenance economics more reliably.

Checklist for Goods Technical Evaluation Criteria

  • Assign pass-or-fail criteria to standardized commodities and scoring to complex equipment or combined quality-price tenders.
  • Set minimum overall technical scores at no less than 70% of total points, or 80% to 90% for high-tech specifications.
  • Verify that no minimum passing score is imposed on non-core detailed sub-criteria.
  • Anchor every point tier to measurable thresholds verifiable against catalogs, factory datasheets, and quality certificates.

Legal Basis & Regulatory Scope

Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Article 58); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Clause 4, Article 26 and Article 29); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.

Filed under: Bid Evaluation & Award #Technical Scoring #Goods Tenders #Article 58 Procurement Law #Decree 214/2025