Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 29, 30, and.
- Key Benchmark: Under Point a, Clause 2, Article 31 of Decree No.
- Execution Control: Require written feasibility justification for zero unit rates on core items without permitting post-closing price changes.
01Regulatory Context & Core Scope
During e-GP price-schedule audits, evaluation panels frequently encounter minor line items left blank or priced at zero inside a bidder's Bill of Quantities. Without applying the exact distinctions in Article 31 of Decree No. 214/2025/ND-CP, panels risk confusing arithmetic error correction, scope deviation adjustment, and abnormally low unit-price verification.
02Pricing Methodology & Cost Controls
Under Point a, Clause 2, Article 31 of Decree No. 214/2025/ND-CP, for works tenders not using lump-sum contracts, where a bidder lists all required work items matching the E-HSMT schedule but leaves unit prices and totals blank on certain items, the omission is not treated as missing scope. Those unpriced items are deemed absorbed into other quoted rates, and the contractor remains obligated to execute them without separate payment.
Conversely, where a bidder drops required work lines entirely from the schedule, the missing line items constitute omitted scope. Evaluators must perform deviation adjustments under Article 31 by adding comparison costs solely for ranking purposes; if total missing-scope deviations exceed the disqualification percentage stated in the E-HSMT, the bid fails responsiveness.
03Procedural Sequence & e-GP Execution
Where an e-GP webform row displays a valid line total with a blank unit price, or a unit rate with a blank line total, Clause 1, Article 31 directs evaluators to perform straightforward arithmetic correction by dividing or multiplying against the controlling tender quantity.
Finally, if a bidder deliberately inputs zero or disproportionately low unit prices on core structural or equipment items to depress its bid total, the investor should require written clarification substantiating material sources and cost build-up without altering the submitted bid price. If the explanation lacks credible feasibility and threatens execution quality, the bid may be rejected under abnormally low pricing safeguards.
Checklist for Blank or Zero Unit Prices on e-GP
- Verify whether the bidder retained all required work descriptions or deleted lines causing omitted scope.
- Apply Clause 1, Article 31 arithmetic correction whenever totals and unit rates are only partially populated.
- Apply Point a, Clause 2, Article 31 to treat listed unpriced lines as absorbed and record non-separate-payment terms in negotiation minutes.
- Require written feasibility justification for zero unit rates on core items without permitting post-closing price changes.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 29, 30, and 31); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.