Key Takeaways
- Extension vs Restoration: Extensions occur before expiry; Clause 33b restoration revives validity after evaluation delays cause expiry.
- No Forfeiture on Refusal: Bidders declining to restore expired bids are excluded from further review without penalty or bond seizure.
- Price Freeze: Restoration merely renews validity and forbids post-opening price or technical revisions.
01Legal Gap When Bid Validity Lapses During Evaluation
Complex tenders requiring similar-contract audits, sample laboratory testing, or complaint resolution regularly stretch evaluation timelines past the original validity window, leaving E-HSDTs and bid securities already expired before an extension request goes out.
02Restoring Expired Bids and Bank Securities Under Clause 33b
Prior to 9 September 2026, once validity lapsed, a traditional extension could not easily revive a dead bank guarantee. Decree 349/2026/ND-CP resolved this gap by introducing Clause 33b into Article 140 of Decree 214/2025/ND-CP, creating an explicit legal mechanism to restore expired E-HSDT and corresponding bid security validity.
Under Clause 33b, when protracted assessment causes validity expiration, the Project Owner notifies affected bidders via e-GP requesting written restoration of E-HSDT validity within a set deadline accompanied by a bank-issued bid-security restoration or re-issuance instrument covering the full extended commitment window.
03Penalty-Free Declination Rights & Proactive Monitoring Controls
Crucially for contractor fairness, Clause 33b guarantees safe exit rights: if a bidder declines to restore expired validity because market costs shifted during the delayed evaluation, its E-HSDT simply ceases to be evaluated further and the bidder suffers zero bid-security forfeiture or compliance penalty.
Nevertheless, Project Owners should still monitor validity countdowns proactively 20 days prior to expiry to request normal extensions first, reserving Clause 33b strictly as a safeguard when unavoidable evaluation delays cause expiration.
Pre-Expiry Extension Versus Post-Expiry Clause 33b Restoration
| Comparison Criteria | Pre-Expiry Extension | Clause 33b Post-Expiry Restoration |
|---|---|---|
| Trigger Timing | Requested prior to original bid expiry date | Triggered after evaluation delays caused expiry |
| Bank Security Instrument | Continuous extension addendum | Restoration letter or re-issued guarantee instrument |
| Effect of Bidder Refusal | No forfeiture outside statutory bounds | Evaluation stops; zero penalty or bond forfeiture |
| Bid Terms Modification | Original prices and technical offer stay frozen | Original prices and technical offer stay frozen |
Five-Step Workflow to Restore Expired Bid Validity Under Clause 33b
- Document objective causes of protracted evaluation that pushed the tender past its initial validity date.
- Send formal e-GP requests instructing eligible bidders to confirm E-HSDT validity restoration in writing.
- Collect matching bank guarantee restoration letters or replacement bid securities covering the new validity term.
- If any bidder declines restoration: stop evaluating that bid in Form 02A and return its bid security unpenalized.
- Prohibit any alteration to original bid prices or technical commitments during the restoration process.
Legal Basis & Regulatory Scope
Clause 33b, Article 140 of Decree 214/2025/ND-CP dated 4 August 2025 (added by Decree 349/2026/ND-CP dated 9 September 2026); Form 02A of Circular 134/2026/TT-BTC.