Bid Evaluation & Award

Drafting and Evaluating Single-Stage Two-Envelope E-HSMT for High-Technology Procurement Packages

Drafting and Evaluating Single-Stage Two-Envelope E-HSMT for High-Technology Procurement Packages
Guide to applying single-stage two-envelope bidding under Article 31 of the Procurement Law, two-round e-GP opening, technical shortlist approval, and opening financial proposals.

Key Takeaways

  • Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Articles 31 and 58); Government Decree No. 214/2025/ND-CP dated 04/08/2025 .
  • Key Benchmark: Document the high-technology basis under science and technology law before approving two-envelope bidding for goods or works.
  • Execution Control: Complete financial error correction, combined scoring, and negotiation where applicable under Article 45 of Decree No. 214/2025/ND-CP.

01Regulatory Context & Core Scope

Single-stage two-envelope bidding shields technical evaluations from price bias by keeping financial proposals sealed until technology, methodology, and quality scores are locked. However, procuring entities cannot apply this method arbitrarily to large routine tenders and must satisfy strict statutory triggers under Article 31 of Law on Procurement No. 22/2023/QH15.

02Procedural Sequence & e-GP Execution

Under Clause 1, Article 31 of Law No. 22/2023/QH15, single-stage two-envelope bidding in open or restricted tenders applies exclusively to consulting services and to non-consulting, goods, works, or mixed packages requiring high technology under science and technology law. When preparing plans and E-HSMTs using Series B templates under Circular No. 79/2025/TT-BTC (such as Forms 3B, 4B, 5B, 11B, and 12B), investors must document the statutory high-technology basis to justify the two-round schedule.

On the e-GP portal, bidders submit separate technical and financial electronic proposals simultaneously before closing. Immediately after bid closing, the procuring entity conducts the first electronic opening covering technical proposals only, while all financial envelopes remain encrypted and inaccessible on the platform.

03Independent Appraisal, Petitions & Audit Trails

The evaluation panel audits eligibility, capability, and technical scoring against approved criteria under Section 2, Chapter III of Decree No. 214/2025/ND-CP and issues a technical evaluation report. Only after the investor formally approves and publishes the list of technically responsive bidders on e-GP does the system unlock the second opening round for those qualifying bidders' financial proposals.

Financial envelopes of bidders failing technical evaluation remain permanently encrypted and unopened. For technically compliant bidders, evaluators complete arithmetic error correction, deviation adjustments, combined or evaluated-price ranking, contract negotiation where applicable under Article 45 of Decree No. 214/2025/ND-CP, and final award approval.

Milestones for Two-Envelope e-GP Tenders

  • Document the high-technology basis under science and technology law before approving two-envelope bidding for goods or works.
  • Select the matching two-envelope Series B templates under Circular No. 79/2025/TT-BTC with transparent technical scoring rubrics.
  • Open only technical envelopes in Round 1 and issue formal technical shortlist approval before decrypting financial envelopes.
  • Complete financial error correction, combined scoring, and negotiation where applicable under Article 45 of Decree No. 214/2025/ND-CP.

Legal Basis & Regulatory Scope

Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15 and 90/2025/QH15 (Articles 31 and 58); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Section 2, Chapter III; Article 45); Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.

Filed under: Bid Evaluation & Award #Two-Envelope Bidding #High Technology #Article 31 Procurement Law #Circular 79/2025
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.