Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (Article 88); Decree 24/2024/ND-CP dated 27 February 2024 (Clauses 5, 6, 8, and 9 of Article 131).
- Key Benchmark: Act within 4 hours of bid closing to issue either a deadline extension or immediate opening order under Clause 5, Article 131.
- Execution Control: Confirm the final price after resubmission or negotiation stays at or below the approved package ceiling.
01Regulatory Context & Core Scope
When an open, restricted, competitive-shopping, or standard online-quotation package receives only one E-HSDT by closing, the Project Owner must not cancel the tender hastily without following Article 88 of Bidding Law 22/2023/QH15 and Article 131 of Decree 24/2024/ND-CP. Observing strict response hours preserves the legal validity of subsequent award steps.
02Procedural Sequence & e-GP Execution
Under Clause 5, Article 131 of Decree 24/2024/ND-CP, where only one or two bidders submit dossiers by closing, the Project Owner has at most 4 hours from closing to choose between extending the submission deadline to attract more competitors or proceeding immediately to bid opening. Under Clause 6, if only one or two bidders remain after a deadline extension, immediate bid opening and evaluation is permitted.
A second scenario arises when several bids are opened but only one bidder clears the technical evaluation stage. Under Clause 9, Article 131 of Decree 24/2024/ND-CP, the Project Owner applies Points a or b of Clause 8 (allowing price resubmission with or without concurrent review of the budget and E-HSMT) or invites that sole technically compliant bidder into price negotiations.
03Pricing Methodology & Cost Controls
If the sole remaining bidder's corrected and adjusted bid exceeds the approved package ceiling, Points a and b of Clause 8 permit price resubmission within up to 10 days or concurrent re-examination of budget assumptions and solicitation terms. Where direct price negotiation is selected under Clause 9, the final negotiated price must never exceed the approved package ceiling.
Across all options, the Project Owner should issue a reasoned decision confirming that the E-HSMT contained no competition-restricting clauses and log every action electronically on e-GP. Both the evaluation report and independent appraisal report must document the Clause 5 or Clause 9 decision chain prior to award approval.
Single-Bidder Situation Handling Checklist
- Act within 4 hours of bid closing to issue either a deadline extension or immediate opening order under Clause 5, Article 131.
- Audit the E-HSMT for restrictive terms before authorizing single-bidder opening.
- Apply Clause 9 alongside Points a and b of Clause 8 or price negotiation when only one bidder passes technical evaluation.
- Confirm the final price after resubmission or negotiation stays at or below the approved package ceiling.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (Article 88); Decree 24/2024/ND-CP dated 27 February 2024 (Clauses 5, 6, 8, and 9 of Article 131).