Key Takeaways
- Governing Scope: Decree 24/2024/ND-CP dated 27 February 2024 (Article 27 and Clause 3, Article 28); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Forms 4A and 4B).
- Key Benchmark: Evaluation panels must never use Article 28 clarification requests to invite a bidder to extend a 12-month warranty to 24 months after bid opening.
- Execution Control: Limit Article 28 clarifications to confirming omitted supporting SLA letters where main bid terms do not conflict.
01Regulatory Context & Core Scope
In medical device, IT infrastructure, MEP equipment, and civil works tenders, minimum warranty duration (such as 24 or 36 months) and onsite incident response times (such as 4 or 24 hours) protect operational continuity after handover. Evaluation panels must distinguish clearly between bids offering shorter warranty terms than required and bids merely omitting supplemental support declarations.
02Contract Performance, Settlement & Amendments
Under Article 27 of Decree 24/2024/ND-CP and Chapter III of Forms 4A and 4B under Circular 06/2024/TT-BKHDT, minimum warranty duration specified in technical specifications and contract conditions constitutes a mandatory compliance threshold. If a bidder explicitly proposes a 12-month warranty against a mandatory 24-month minimum, the bid fails technical evaluation and cannot advance to financial scoring.
Evaluation panels must never use Article 28 clarification requests to invite a bidder to extend a 12-month warranty to 24 months after bid opening. Extending warranty liability post-closing alters core technical obligations and underlying risk pricing in breach of Clause 3, Article 28 of Decree 24/2024/ND-CP.
03Core Regulatory Provisions & Conditions
By contrast, where a bidder confirms full compliance with the 24-month warranty inside its main technical table yet omits a standalone SLA letter confirming onsite response hours, the panel should check whether Chapter III makes that standalone letter a pass-or-fail gate. Provided the E-HSDT contains no contradictory response times, the Procuring Entity may seek written confirmation under Article 28 without altering core scope or bid price.
To prevent ambiguity altogether, drafting teams should reconcile warranty months and onsite repair turnaround rules identically across Chapter III evaluation tables, Chapter V technical specifications, and Special Conditions of Contract prior to e-GP publication.
Warranty & SLA Evaluation Checklist
- Verify identical warranty duration and SLA response metrics across Chapters III, V, and contract terms before release.
- Fail bids at technical evaluation whenever offered warranty duration falls below the E-HSMT minimum.
- Never allow bidders to lengthen an explicitly shorter warranty period via post-closing clarification.
- Limit Article 28 clarifications to confirming omitted supporting SLA letters where main bid terms do not conflict.
Legal Basis & Regulatory Scope
Decree 24/2024/ND-CP dated 27 February 2024 (Article 27 and Clause 3, Article 28); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter III, Forms 4A and 4B).