Key Takeaways
- Governing Scope: Point b, Clause 5, Article 26 and Clause 2, Article 29 of Decree 214/2025/ND-CP; Model 3A of Circular 79/2025/TT-BTC.
- Key Benchmark: Extract and lock every atomic requirement from Chapters III and V of the E-HSMT prior to reading any bidder proposal.
- Execution Control: Anchor every pass or fail conclusion in the Bid Evaluation Report to exact section and page citations in the E-HSDT.
01Regulatory Context & Core Scope
Under Point b, Clause 5, Article 26 of Decree 214/2025/ND-CP and Model 3A of Circular 79/2025/TT-BTC, technical evaluation for civil works centers on the rationality and feasibility of engineering solutions and construction method statements aligned with proposed schedules, site management, quality control, occupational safety, fire protection, and environmental mitigation. Panels are prohibited from embedding key personnel or major equipment mobilization requirements into technical evaluation to eliminate bidders, as domestic works packages verify detailed staff and equipment for the first-ranked bidder under Clause 2, Article 29 of Decree 214/2025/ND-CP.
02Independent Appraisal, Petitions & Audit Trails
A substantive construction method statement grounded in Chapter V of the E-HSMT defines work sequence and start prerequisites across major trades, lays out site logistics including haul roads, laydown zones, storage sheds, temporary power, water, and drainage, addresses traffic safety and underground utility protection, and maps concealed works plus mandatory inspection hold points prior to backfilling or follow-on phases.
By contrast, copied or generic submissions reveal four telltale flaws upon full reading: leftover names of other municipalities, project owners, or structures unrelated to the package; detailed narratives for trades absent from the bill of quantities and issued drawings; narrative durations or crew sequences contradicting the submitted master schedule; or key material schedules that merely write compliant without identifying supply origins, permitted brand groups, or technical datasheets.
03Validity Boundaries & Common Evaluation Pitfalls
At the same time, evaluators must avoid subjective rejections merely because prose is concise when core Chapter III and Chapter V criteria are satisfied. Panels should examine whether the proposed method is physically buildable under actual site constraints and consistent with the construction schedule, noting that bidders may propose alternative construction methods unless the E-HSMT explicitly mandates a single method.
Every pass or fail finding recorded in Form 04A or 04B of the Bid Evaluation Report must cite the exact chapter and page of the bidder narrative, quote the verbatim Chapter III E-HSMT requirement, and document specific omissions or contradictions. Evidence-anchored evaluation notes withstand independent appraisal and formal bid protests.
Checklist for Auditing Civil Works Method Statements
- Extract and lock every atomic requirement from Chapters III and V of the E-HSMT prior to reading any bidder proposal.
- Cross-check consistency across the method narrative, site layout drawing, key materials table, and master construction schedule.
- Screen for copy-paste indicators such as mismatched locations, wrong project titles, out-of-scope trades, or conflicting sequences.
- Keep key personnel and equipment mobilization verification separate from technical evaluation scoring in domestic tenders.
- Anchor every pass or fail conclusion in the Bid Evaluation Report to exact section and page citations in the E-HSDT.
Legal Basis & Regulatory Scope
Point b, Clause 5, Article 26 and Clause 2, Article 29 of Decree 214/2025/ND-CP; Model 3A of Circular 79/2025/TT-BTC; Forms 02A and 02B of Circular 134/2026/TT-BTC.