Key Takeaways
- Governing Scope: Point b, Clause 4, Article 16 of Bidding Law 22/2023/QH15; Clause 2 of Article 26, Clause 2 of Article 29, Article 30, and Article 133 of Decree 214/2025/ND-CP.
- Key Benchmark: When evaluating domestic works E-HSDTs on e-GP, panels must follow Clause 2, Article 29 of Decree 214/2025/ND-CP.
- Execution Control: Verify certificate validity dates and issuer credentials, disqualifying immediately where document tampering is confirmed.
01Regulatory Context & Core Scope
Major civil, bridge, and industrial works tenders routinely require tower cranes, construction hoists, aerial lifts above 2 meters, electric winches, or pressure vessels. These machines fall on the strict occupational safety list under Circular 36/2019/TT-BLDTBXH and require valid technical safety inspection certificates under Law 84/2015/QH13 and Decree 44/2016/ND-CP.
02Procedural Sequence & e-GP Execution
When evaluating domestic works E-HSDTs on e-GP, panels must follow Clause 2, Article 29 of Decree 214/2025/ND-CP. Initial review relies on the contractor's mobilization commitment in the Bid Submission Letter rather than immediately rejecting webform entries on Form 06D; detailed verification of each listed machine and attached document is performed after financial evaluation strictly for the first-ranked bidder.
During detailed verification and document comparison, reviewers check three evidentiary layers for safety-critical equipment: proof of ownership or a binding lease agreement backed by the lessor's ownership title; technical capacity matching Section 2.2, Chapter III of Template 3A; and an unexpired Technical Safety Inspection Certificate issued by a licensed inspection organization.
03Qualification Benchmarks & Bidder Preferences
If a proposed machine lacks a current inspection certificate, holds an expired certificate at bid closing, or relies on a lease lacking title proof, the panel cannot disqualify immediately. Under Clause 2, Article 29 and Article 30 of Decree 214/2025/ND-CP, the first-ranked domestic works bidder may clarify and replace or supplement each non-compliant equipment slot up to two times to honor its bid commitment.
Substitution rights never shield falsification. Where verification with the issuing inspection center reveals altered expiry dates, forged serial numbers, or fabricated signatures, Clause 2, Article 29 bars replacement, disqualifies the bid for fraud under Point b, Clause 4, Article 16 of Bidding Law 22/2023/QH15, and triggers debarment under Clause 1, Article 133 of Decree 214/2025/ND-CP.
Checklist for Safety-Inspected Construction Equipment Verification
- Flag all machines declared on Form 06D that fall under the mandatory inspection list of Circular 36/2019/TT-BLDTBXH.
- Conduct detailed equipment verification for the first-ranked bidder after financial scoring and allow up to two replacement rounds per non-compliant slot.
- Cross-check ownership invoices or lease title chains so machine serial numbers match safety inspection certificates.
- Verify certificate validity dates and issuer credentials, disqualifying immediately where document tampering is confirmed.
Legal Basis & Regulatory Scope
Point b, Clause 4, Article 16 of Bidding Law 22/2023/QH15; Clause 2 of Article 26, Clause 2 of Article 29, Article 30, and Article 133 of Decree 214/2025/ND-CP; Circular 79/2025/TT-BTC (Template 3A, Form 06D); Law on Occupational Safety and Hygiene 84/2015/QH13; Decree 44/2016/ND-CP; and Circular 36/2019/TT-BLDTBXH.