Operating Simplified Online Quotations for Civil Works Packages From 1 September 2025 Under Circular 79/2025/TT-BTC

Operating Simplified Online Quotations for Civil Works Packages From 1 September 2025 Under Circular 79/2025/TT-BTC
Guide to deploying Form 12E under Circular 79/2025/TT-BTC and the VND 2B to 5B eligibility limits under Clause 3, Article 99 of Decree 214/2025/ND-CP for simplified online works quotations starting 1 September 2025.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Clause 3 Article 99).
  • Key Benchmark: Verify package ceilings fall within VND 2 billion (recurrent) or VND 5 billion (project) limits under Clause 3, Article 99 of Decree 214/2025/ND-CP.
  • Execution Control: Audit technical responsiveness and legal eligibility of the lowest-priced bidder prior to final award sign-off.

01Regulatory Context & Core Scope

Effective 1 September 2025, Vietnam's e-GP system activated simplified online quotation workflows specifically for civil works packages under the staggered commencement clause of Circular 79/2025/TT-BTC. This expansion brings real-time electronic reverse-bidding competition to small and medium repair, upgrade, and construction tenders.

02Pricing Methodology & Cost Controls

Under Clause 3, Article 99 of Decree 214/2025/ND-CP, simplified online quotations apply to works packages capped at VND 2 billion under recurrent procurement budgets and up to VND 5 billion under investment projects. Project Owners designate this method inside the approved contractor selection plan to accelerate tendering timelines.

On e-GP, Project Owners prepare tender packages using Form 12E under Clause 12, Article 4 of Circular 79/2025/TT-BTC, created expressly for works alongside Forms 12A to 12D for goods and non-consulting services. Form 12E comprises three structured parts: Part 1 defines online bidding rules, price decrements, and live bidding windows; Part 2 sets technical specifications, bills of quantities, and construction standards; and Part 3 provides quotation schedules and draft contract terms.

03Procedural Sequence & e-GP Execution

Operationally, participating contractors submit iterative lower bids during the live online quotation window while e-GP displays the leading lowest price in real time without exposing bidder identities, driving transparent price discovery.

Once the bidding clock closes, the evaluation panel must still verify eligibility and binding compliance with drawings, material grades, and execution schedules in Part 2 of Form 12E before awarding the contract, preventing reckless underbidding by unqualified contractors.

Simplified Online Quotation for Civil Works (Form 12E Circular 79/2025)

ParameterRecurrent Budget PackageInvestment Project Package
Civil Works Budget CapUp to VND 2,000,000,000Up to VND 5,000,000,000
Mandatory e-GP TemplateForm 12E (Clause 12 Art. 4 Circular 79/2025)Form 12E with drawings, BOQ and technical specs
Post-Bidding Award RuleLowest price plus technical and eligibility verificationVerify full Part 2 engineering & schedule compliance

Simplified Online Works Quotation Checklist (Form 12E)

  • Verify package ceilings fall within VND 2 billion (recurrent) or VND 5 billion (project) limits under Clause 3, Article 99 of Decree 214/2025/ND-CP.
  • Draft tender documents on e-GP strictly using Form 12E of Circular 79/2025/TT-BTC.
  • Calibrate realistic minimum bid decrements and publish clear start and end timestamps for live quotation rounds.
  • Attach complete drawings, bills of quantities, and material specifications in Part 2 so bidders price works accurately.
  • Audit technical responsiveness and legal eligibility of the lowest-priced bidder prior to final award sign-off.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Clause 3 Article 99); Circular 79/2025/TT-BTC (Clause 12 Article 4, Form 12E, works module effective 1 September 2025).

Filed under: Sectoral Tenders (Health, IT, Works) #Simplified Online Quotation #Works Packages #Form 12E #Circular 79/2025
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.