Key Takeaways
- Sub-5B Competitive Works: Bidding Law Article 10 reserves open and competitive-quote works <= 5B VND exclusively for small and micro-enterprises.
- Audit Concurrent Capacity: Repeating direct awards to a single vendor requires strict checks against overlapping site personnel and equipment.
- Check Portal Toggles: Verify enterprise-size eligibility switches before releasing notices on e-GP.
01Two High-Scrutiny Controls in Small-and-Mid Works Packages
As direct-contracting thresholds rise and local infrastructure packages frequently fall under 5 billion VND, state inspectors increasingly examine two high-risk areas: repeatedly nominating the same contractor across multiple packages and correctly applying small-and-micro enterprise reservations.
02Auditing Repeated Direct Contracting to One Firm in a Project
First, under Point b, Clause 3, Article 79 and Point a, Clause 3, Article 80 of Decree 214/2025/ND-CP (as amended by Decree 349/2026/ND-CP), when awarding multiple direct-contracted packages within the same investment project, Project Owners must audit concurrent capacity limits, legal-financial independence, and any applicable concentration restrictions before repeating the same nominee.
Assigning multiple sub-ceiling packages to one familiar vendor risks simultaneous key-personnel and equipment overlaps across parallel construction sites as well as anti-splitting inquiries.
03Small & Micro-Enterprise Reservation Rule for Works <= 5B VND
Second, for competitive construction tenders (open bidding or competitive quotation) valued up to 5 billion VND (including sub-2-billion packages), Point dd, Clause 2, Article 10 of Bidding Law 22/2023/QH15 mandates reserving participation exclusively for small and micro-enterprises, unless an initial attempt finds no qualified small or micro bidder.
Forgetting to toggle the small and micro-enterprise reservation flag when configuring a 3-billion or 4-billion-VND e-GP works solicitation creates an immediate eligibility defect, inviting bidder complaints and forced E-HSMT addenda or re-tenders.
Participation Rules for Works Packages Valued at or Below 5 Billion VND
| Selection Method | Eligible Bidders | Key Compliance Check |
|---|---|---|
| Open tender / competitive quotation <= 5B VND | Small and micro-enterprises exclusively | Enable Article 10 portal flag and verify headcount/turnover class |
| Re-tender after Round 1 finds no compliant SME | Open to enterprises of all sizes | Archive Round-1 proof showing no eligible small/micro bidder |
| Multiple direct awards in one project | Independent, capable single contractors | Verify non-overlapping key staff/plant under Articles 79 & 80 |
| Joint venture in reserved <= 5B works | Every JV partner must be small or micro | Disqualify JV if any member classifies as medium or large |
Compliance Checklist for Works Packages Under 5 Billion VND
- Enable the mandatory small/micro-enterprise reservation setting on e-GP for competitive works tenders <= 5B VND.
- Verify bidder employee headcount and revenue declarations to confirm statutory small/micro-enterprise status.
- Cross-check key staff and machinery schedules whenever nominating one firm across multiple direct-contracted lots.
- Confirm strict independence between the nominated contractor, Project Owner, and design/supervision consultants.
- Open sub-5B works tenders to medium or large enterprises only after an unsuccessful first round reserved for small firms.
Legal Basis & Regulatory Scope
Point dd, Clause 2, Article 10 of Bidding Law 22/2023/QH15; Point b, Clause 3, Article 79 and Point a, Clause 3, Article 80 of Decree 214/2025/ND-CP (amended by Decree 349/2026/ND-CP).