Bid Evaluation & Award

Handling Bidder Refusal to Confirm Arithmetic Corrections or Deviation Adjustments Issued by the Evaluation Panel

Handling Bidder Refusal to Confirm Arithmetic Corrections or Deviation Adjustments Issued by the Evaluation Panel
Explaining notification steps, the 3-business-day bidder confirmation deadline, and the exception preventing disqualification if the Procuring Entity miscalculated corrections under Article 29 of Decree 24/2024/ND-CP.

Key Takeaways

  • Governing Scope: Decree 24/2024/ND-CP dated 27 February 2024 (Article 29); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter I Instructions to Bidders on error correction and de.
  • Key Benchmark: Under Article 29, a bidder that refuses valid arithmetic corrections or deviation adjustments has its E-HSDT rejected.
  • Execution Control: Archive notices, bidder replies, and panel re-check minutes inside the formal evaluation dossier.

01Regulatory Context & Core Scope

Even with e-GP webform totals, arithmetic errors between unit prices and line totals, discrepancies between figures and words in attached schedules, or missing and extra scope items still occur in complex and mixed packages. Resolving these discrepancies strictly follows Article 29 of Decree 24/2024/ND-CP so competing bids are compared on a level financial baseline.

02Validity Boundaries & Common Evaluation Pitfalls

Under Article 29 of Decree 24/2024/ND-CP, the evaluation panel first corrects arithmetic mistakes and adjusts omissions or excesses relative to the E-HSMT scope by applying reference unit rates. Once the worksheet is complete, the Procuring Entity must send a written notice via e-GP detailing each adjusted line item and revised total.

Within 3 business days of receiving that notice, the bidder must reply in writing stating whether it accepts or rejects the arithmetic corrections, deviation adjustments, and applied reference unit prices. This 3-business-day window ensures transparent review before financial ranking proceeds.

03Pricing Methodology & Cost Controls

Under Article 29, a bidder that refuses valid arithmetic corrections or deviation adjustments has its E-HSDT rejected. Critically, the regulation carves out an explicit safeguard: the bid must not be rejected if the bidder's refusal stems from the Procuring Entity's corrections, adjustments, or applied unit prices being inaccurate or inconsistent with the rules.

Accordingly, if a bidder responds with calculations proving the panel misapplied a reference rate or misread an inclusive line item, the evaluation panel must re-audit its worksheet objectively rather than disqualifying automatically. Rejection is lawful only when the panel confirms full compliance with Article 29 and the bidder still refuses or fails to confirm within the deadline.

Arithmetic & Deviation Correction Checklist

  • Distinguish arithmetic mistakes cleanly from quantity deviations under Article 29 of Decree 24/2024/ND-CP.
  • Send an itemized correction notice via e-GP giving the bidder 3 business days to confirm in writing.
  • Re-audit panel calculations whenever a bidder objects with reasoned proof of panel miscalculation.
  • Archive notices, bidder replies, and panel re-check minutes inside the formal evaluation dossier.

Legal Basis & Regulatory Scope

Decree 24/2024/ND-CP dated 27 February 2024 (Article 29); Circular 06/2024/TT-BKHDT dated 26 April 2024 (Chapter I Instructions to Bidders on error correction and deviation adjustment).

Filed under: Bid Evaluation & Award #Arithmetic Correction #Deviation Adjustment #Article 29 Decree 24/2024 #Financial Evaluation