Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (Article 24); Decree 214/2025/ND-CP (Articles 26, 28, 81, and 140).
- Key Benchmark: Confirm package ceiling does not exceed VND 10 billion and qualifies as standardized goods, non-consulting, or simple works.
- Execution Control: Demand written feasibility substantiation whenever abnormally low bid pricing surfaces before award.
01Regulatory Context & Core Scope
Online competitive shopping targets standardized off-the-shelf goods, simple non-consulting services, and straightforward civil works with approved construction drawings. Under Clause 1, Article 81 of Decree 214/2025/ND-CP, the ceiling spans up to VND 10 billion, letting Project Owners accelerate standardized procurement while keeping open competition intact.
02Procedural Sequence & e-GP Execution
Article 81 streamlines preparation significantly: Project Owners approve competitive-shopping E-HSMTs directly from submission memos without mandatory E-HSMT appraisal, providing a minimum 7-working-day bid preparation window on e-GP. Crucially, non-consulting competitive shopping packages must exclude capability and experience criteria altogether, while goods and works packages may accept capability declarations depending on package complexity.
To deploy cleanly under Circular 79/2025/TT-BTC (Form 3A for works, Form 4A for goods, Form 5A for non-consulting), Chapter V technical specifications should remain concise and evaluated strictly on pass or fail criteria, avoiding ambiguous metrics or mismatched measurement units.
03Contract Performance, Settlement & Amendments
During bid evaluation, panels must apply arithmetic and deviation rules accurately. Under Circular 79/2025/TT-BTC guidance, lump-sum bids are deemed inclusive of all design-specified scope, meaning minor line-item schedule variations are not adjusted unless genuinely extraneous items appear outside E-HSMT scope. For unit-price contracts, omitted required line items are priced and added for fair bid comparison.
Where an evaluated bid falls abnormally low (such as below 80% for works) or where all technically responsive bids exceed the approved package ceiling, the Project Owner invokes situational remedies under Article 140 of Decree 214/2025/ND-CP to demand feasibility explanations or conduct re-bidding rounds.
Online Competitive Shopping Control Checklist
- Confirm package ceiling does not exceed VND 10 billion and qualifies as standardized goods, non-consulting, or simple works.
- Provide at least 7 working days for e-GP bid preparation and omit capability criteria on non-consulting packages.
- Draft unambiguous pass or fail technical criteria synchronized with webform units of measurement.
- Apply distinct deviation-adjustment rules tailored accurately to lump-sum versus unit-price contract types.
- Demand written feasibility substantiation whenever abnormally low bid pricing surfaces before award.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (Article 24); Decree 214/2025/ND-CP (Articles 26, 28, 81, and 140); Circular 79/2025/TT-BTC (Forms 3A, 4A, and 5A).