Key Takeaways
- Governing Scope: Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Articles 30 and 38).
- Key Benchmark: Select the exact template series under Article 4 of Circular 79/2025/TT-BTC: 7A to 7C (EP), 8A to 8C (EC), 9A to 9C (PC), or 10A to 10C (EPC).
- Execution Control: Align bid security templates and lump-sum or unit-price contract terms with EPC risk allocation.
01Regulatory Context & Core Scope
Mixed procurement packages (Engineering and Procurement [EP], Engineering and Construction [EC], Procurement and Construction [PC], or full EPC) involve substantial capital values and tightly coupled engineering interfaces. Choosing the wrong template or blurring design qualifications with equipment supply and civil construction criteria inside the E-HSMT routinely disrupts evaluation.
02Procedural Sequence & e-GP Execution
Clauses 7 through 10, Article 4 of Circular 79/2025/TT-BTC assign dedicated e-GP forms for each mixed model: Forms 7A to 7C for EP, Forms 8A to 8C for EC, Forms 9A to 9C for PC, and Forms 10A to 10C for EPC packages. Suffix 'A' denotes one-stage one-envelope tenders, 'B' covers one-stage two-envelope tenders, and 'C' governs e-prequalification documents (E-HSMST).
When structuring Chapter III evaluation criteria, drafters must separate prior experience and staffing thresholds across each functional discipline. Under joint ventures for EP or EPC packages, qualification aggregation must reflect the exact scope allocated in the joint-venture agreement, matching design capacity certificates to the engineering partner and fabrication or installation credentials to the equipment and construction partners.
03Qualification Benchmarks & Bidder Preferences
For domestic mixed packages containing construction works (such as EC and PC), evaluation panels apply the streamlined rule under Article 30 of Decree 214/2025/ND-CP: clarification and supporting evidence for key construction personnel and primary machinery are requested only from the first-ranked bidder, saving weeks of redundant preliminary verification.
Within technical specifications and contract terms, the E-HSMT must lock down interface testing responsibilities, integrated commissioning milestones, and operator handover obligations. Requiring separate price schedules across engineering, equipment supply, and site installation equips Project Owners to certify milestone payments accurately.
Mixed Package E-HSMT Control Checklist
- Select the exact template series under Article 4 of Circular 79/2025/TT-BTC: 7A to 7C (EP), 8A to 8C (EC), 9A to 9C (PC), or 10A to 10C (EPC).
- Segregate engineering, equipment supply, and construction experience requirements proportional to joint-venture scope splits.
- Apply Article 30 of Decree 214/2025/ND-CP so key works staff and equipment evidence is requested only from the top-ranked domestic EC or PC bidder.
- Separate price schedules, payment milestones, and integrated commissioning liabilities clearly in technical and contract chapters.
- Align bid security templates and lump-sum or unit-price contract terms with EPC risk allocation.
Legal Basis & Regulatory Scope
Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Articles 30 and 38); Circular 79/2025/TT-BTC (Clauses 7 to 10 Article 4).