Key Takeaways
- Governing Scope: Article 61 and Clause 4, Article 68 of Bidding Law 22/2023/QH15; Clause 2 of Article 29 and Clause 11 of Article 131 of Decree 24/2024/ND-CP.
- Key Benchmark: Check the 70% package-budget threshold on works tenders and flag unit rates deviating sharply from approved cost estimates.
- Execution Control: Exclude notional deviation adjustments from the award price and enforce strict quality controls in contract administration.
01Regulatory Context & Core Scope
Abnormally low total bids or near-zero unit prices on critical work items create significant risk of material substitution, schedule slippage, or opportunistic variation claims during execution. Under Clause 11, Article 131 of Decree 24/2024/ND-CP, an evaluation panel cannot automatically disqualify a low-priced E-HSDT without first conducting a structured feasibility review.
02Pricing Methodology & Cost Controls
Situational review is triggered whenever an evaluated bid price after error correction and discount subtraction appears abnormally low enough to threaten contract quality, and automatically for construction works bids falling below 70% of the approved package budget. The procuring entity must issue a formal clarification request requiring the bidder to substantiate cost breakdowns, construction methodology, supply sources, and compliance with E-HSMT schedules.
Where the bidder demonstrates credible cost advantages such as depreciated in-house machinery, nearby quarry access, or verified supplier rebates, the Project Owner accepts the bid price and continues normal ranking. Conversely, if the written explanation lacks verifiable cost justification or fails to prove technical feasibility, the Project Owner rejects the abnormal pricing claim.
03Validity Boundaries & Common Evaluation Pitfalls
Upon rejection, the abnormally low unit-price items are treated as missing-item deviations and adjusted upward under Clause 2, Article 29 of Decree 24/2024/ND-CP solely for bid comparison and ranking. If the bidder still ranks first after that adjustment, the proposed award price excludes the notional adjustment amount, binding the contractor to deliver at its original quoted prices.
Where a bidder leaves a unit price blank or quotes zero on a line item, that cost is deemed distributed across other bid items, meaning no separate payment will be made while full technical execution remains mandatory. Project Owners should also establish prudent performance security within the statutory range of Clause 4, Article 68 of Bidding Law 22/2023/QH15 and enforce strict site material inspections.
Steps for Reviewing Abnormally Low Bid Unit Prices
- Check the 70% package-budget threshold on works tenders and flag unit rates deviating sharply from approved cost estimates.
- Issue written clarification requests demanding proof of material, labor, equipment, and supply-chain cost structures.
- Assess feasibility evidence objectively; if unconvincing, apply upward deviation adjustment under Clause 2, Article 29 of Decree 24/2024/ND-CP for ranking.
- Exclude notional deviation adjustments from the award price and enforce strict quality controls in contract administration.
Legal Basis & Regulatory Scope
Article 61 and Clause 4, Article 68 of Bidding Law 22/2023/QH15; Clause 2 of Article 29 and Clause 11 of Article 131 of Decree 24/2024/ND-CP; Circular 22/2024/TT-BKHDT; Circular 23/2024/TT-BKHDT.