Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Article 5; Point c, Clause 3,.
- Key Benchmark: Deliberate withholding of verification originals to hand the award to another bidder constitutes prohibited collusion under Point c, Clause 3, Article 16 of the Procurement Law.
- Execution Control: Archive time-stamped registry screenshots and signed original-document verification minutes inside the tender file.
01Regulatory Context & Core Scope
When evaluating a top-ranked joint venture, a hazardous error is auditing only the lead partner closely while overlooking the live legal standing of minority members. Under Article 5 of Law on Procurement No. 22/2023/QH15, every member of a joint venture must independently satisfy legal eligibility; if even one partner faces enterprise-certificate revocation or insolvency proceedings, the entire consortium fails award eligibility.
02Effective Dates & Transitional Scope
The first pre-award check requires querying the enterprise registration number of every joint-venture partner simultaneously on the National Business Registration Portal and e-GP records. Panels must confirm each member maintains active operational status, independent financial accounting, no ongoing dissolution proceedings, no indefinite business suspension, and no insolvency status under Law on Recovery and Bankruptcy No. 142/2025/QH15 effective from 01/03/2026.
Alongside corporate registry status, evaluation teams must verify each member's profile on the National e-Procurement System. Under Point d, Clause 1, Article 5 of the Procurement Law, every contractor must be registered on e-GP before award approval and must remain free of fee-default account locks or active debarment orders issued by any ministry or provincial authority.
03Pricing Methodology & Cost Controls
During original-document verification for the first-ranked joint venture under Decree No. 214/2025/ND-CP and Circular No. 79/2025/TT-BTC, evaluators must examine originals or certified copies of the joint-venture agreement, member authorizations, financial statements, similar contracts, and tax filings mapped to each partner's assigned work share. Deliberate withholding of verification originals to hand the award to another bidder constitutes prohibited collusion under Point c, Clause 3, Article 16 of the Procurement Law.
Before submitting the award recommendation, evaluation and appraisal teams should assemble a cross-check table logging the query timestamp and corporate-status screenshots for each consortium partner from official portals. Preserving that verification trail protects the investor if any partner's corporate standing changes right after award publication.
Eligibility Cross-Check List for Joint Venture Members
- Query enterprise IDs for every joint-venture partner on the National Business Registration Portal prior to award submission.
- Verify active e-GP registration status and check debarment records individually for each consortium member.
- Inspect the original joint-venture agreement, work-share breakdown, and valid signatory authorizations.
- Archive time-stamped registry screenshots and signed original-document verification minutes inside the tender file.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Article 5; Point c, Clause 3, Article 16); Law on Recovery and Bankruptcy No. 142/2025/QH15; Government Decree No. 214/2025/ND-CP dated 04/08/2025; Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025.