Joint Venture Naming, Lead Member Submission, and Bid Security Rules on e-GP Under Circular 01/2024/TT-BKHDT

Joint Venture Naming, Lead Member Submission, and Bid Security Rules on e-GP Under Circular 01/2024/TT-BKHDT
Guidance on drafting joint venture agreements, matching names across e-GP webforms, authorizing the lead member to submit bids, and issuing uniform consortium bid securities under Circular 01/2024/TT-BKHDT.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 14); Circular 01/2024/TT-BKHDT dated 15 February 2024 (replacing Circular 08/2022/TT-BKHDT, Article 32).
  • Key Benchmark: Match the exact consortium name across the Joint Venture Agreement, e-GP webform, bid submission letter, and bank guarantee.
  • Execution Control: Use a uniform bid security format (all electronic or all scanned paper) across every joint venture member.

01Regulatory Context & Core Scope

Effective 15 February 2024, Circular 01/2024/TT-BKHDT replaced Circular 08/2022/TT-BKHDT, aligning E-HSMT forms and joint venture bid submissions on the National e-Procurement System. For large multi-trade packages, mismatched consortium names or incomplete liability wording on bid securities frequently trigger validity rejections.

02Security Validity & Commitment Scope

Regarding naming and system authority, members must execute a Joint Venture Agreement prior to bid submission using an identical consortium name across the agreement, e-GP webform, submission letter, and bank guarantee. The agreement must designate one lead member authorized to use its e-GP account and digital signature to upload the E-HSDT and handle formal clarifications.

Under Circular 01/2024/TT-BKHDT templates, the Joint Venture Agreement must itemize each partner's work scope, percentage share, and joint and several liabilities. Authorized representatives of every member must sign and seal or digitally sign the agreement for it to take effect.

03Qualification Benchmarks & Bidder Preferences

For consortium bid securities, all members must use the same instrument format, either all electronic guarantees or all scanned paper guarantees. Partners may either furnish individual guarantees summing to the required total or authorize the lead member to post one guarantee covering the entire consortium, provided the Joint Venture Agreement explicitly records that delegation.

Where the lead member issues security for the whole consortium, the guarantee must name the joint venture and identify the lead member acting on its behalf while covering forfeiture triggered by any member's breach under Article 14 of Bidding Law 22/2023/QH15. Cross-checking wording across the agreement and guarantee before closing prevents technical disqualifications.

e-GP Joint Venture Submission Checklist

  • Match the exact consortium name across the Joint Venture Agreement, e-GP webform, bid submission letter, and bank guarantee.
  • Specify each partner's percentage work share and explicit authorization for the lead member to submit the bid and arrange security.
  • Obtain valid signatures and seals or digital signatures from all consortium members before the closing timestamp.
  • Use a uniform bid security format (all electronic or all scanned paper) across every joint venture member.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 14); Circular 01/2024/TT-BKHDT dated 15 February 2024 (replacing Circular 08/2022/TT-BKHDT, Article 32).

Filed under: E-HSMT & Budgeting #Joint Venture Bidder #Joint Venture Agreement #Circular 01/2024 #Bid Security
Practical Follow-up: For package-specific inquiries, email info@vntender.com or call 0967 398 664.