Eligibility Conditions for Direct Procurement From Prior Open Tenders or Competitive Shopping Under Law 2023 and Decree 24/2024

Eligibility Conditions for Direct Procurement From Prior Open Tenders or Competitive Shopping Under Law 2023 and Decree 24/2024
Clarifying Article 25 of Law 22/2023/QH15 and Article 80 of Decree 24/2024/ND-CP: direct procurement applies only after prior open or restricted tenders under 130% quantity and 12-month limits, excluding competitive shopping.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 25); Government Decree 24/2024/ND-CP dated 27 February 2024 (Article 80).
  • Key Benchmark: Point a, Clause 2, Article 25 of Law 22/2023/QH15 explicitly requires the prior contract to have been awarded through open bidding or restricted bidding.
  • Execution Control: Benchmark current market unit rates during finalization to ensure prices never exceed the prior contract.

01Regulatory Context & Core Scope

When additional supplies or medical devices matching a prior contract are needed, Project Owners often ask whether a previous competitive shopping award qualifies as the anchor for direct procurement. The exact boundary is governed by Clause 2, Article 25 of Bidding Law 22/2023/QH15 and procedural Article 80 of Decree 24/2024/ND-CP.

02Pricing Methodology & Cost Controls

Point a, Clause 2, Article 25 of Law 22/2023/QH15 explicitly requires the prior contract to have been awarded through open bidding or restricted bidding. Consequently, contracts awarded via competitive shopping, direct appointment, or online quotation are legally ineligible to serve as the predicate for direct procurement.

In addition to the predicate tender method, Clause 2, Article 25 imposes three cumulative limits: direct procurement may be applied only once for those goods, with item quantities strictly below 130% of the prior signed contract (excluding any repeat-order option); unit prices must not exceed the prior contract rates and must match prevailing market prices during contract finalization; and no more than 12 months may elapse from prior contract signing to approval of the direct procurement result.

03Core Regulatory Provisions & Conditions

Procedurally, under Article 80 of Decree 24/2024/ND-CP, the Project Owner issues a Request for Proposals requiring the prior contractor to update eligibility and qualification credentials if circumstances changed. If the original contractor cannot supply, Clause 3, Article 25 allows extending direct procurement to another bidder meeting the original tender criteria and price.

During planning reviews, VNTender emphasizes separating Article 25 direct procurement from pre-announced 30% repeat-order options inside original E-HSMTs. Where the predicate package used competitive shopping, owners must initiate a fresh competitive selection rather than proposing direct procurement.

Four-Point Eligibility Checklist for Article 25 Direct Procurement

  • Confirm the predicate contract was awarded via open or restricted bidding rather than competitive shopping.
  • Verify no more than 12 months separate the predicate contract signing date and expected direct-procurement approval.
  • Check that each item quantity stays below 130% of the prior contract (excluding repeat-order options) and is used only once.
  • Benchmark current market unit rates during finalization to ensure prices never exceed the prior contract.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 dated 23 June 2023 (Article 25); Government Decree 24/2024/ND-CP dated 27 February 2024 (Article 80).

Filed under: E-HSMT & Budgeting #Direct Procurement #Article 25 Law 22/2023 #Article 80 Decree 24 #Competitive Shopping