Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Clauses 5, 6, and 8, Article .
- Key Benchmark: Under Clause 5, Article 14 of Law on Procurement No.
- Execution Control: Release or return bid securities within 14 days when a bidder submits a valid written refusal to extend.
01Regulatory Context & Core Scope
When bid evaluation, document clarification, or independent appraisal extends beyond the planned schedule, a recurring procedural bottleneck occurs when E-HSDT validity and bid security expire before award approval.
Under Clause 5, Article 14 of Law on Procurement No. 22/2023/QH15, bid security validity must equal the E-HSDT validity period plus 30 calendar days to preserve a legal buffer through contract finalization. Evaluation panels should maintain a calendar tracker anchored to the bid-closing date from the moment bids are opened on e-GP.
02Security Validity & Commitment Scope
Under Clause 6, Article 14 of Law No. 22/2023/QH15, whenever E-HSDT validity needs extension after bid closing, the procuring entity or investor must issue a formal written request requiring bidders to extend bid security validity for a matching duration. Bidders agreeing to extend must submit formal validity-extension confirmation alongside a corresponding bank-guarantee amendment or surety endorsement without altering technical proposals or bid prices already submitted.
In procurement practice under Clause 16, Article 140 of Decree No. 214/2025/ND-CP, validity checks also arise when the first-ranked bidder declines contract negotiation or fails to sign the negotiation minutes and the investor invites the next-ranked bidder. If the next-ranked bidder's E-HSDT has already lapsed, the investor must formally request an extension of both the E-HSDT and the bid security before commencing contract negotiation.
03Core Regulatory Provisions & Conditions
Statutory rules draw a clear boundary between a bidder's lawful refusal to extend and bid-security forfeiture. Clause 6, Article 14 of Law No. 22/2023/QH15 provides that if a bidder declines an extension request during prolonged evaluation, its E-HSDT becomes invalid and is rejected, yet the bid security must be released within 14 days from receipt of the refusal notice.
Conversely, if a bidder confirms E-HSDT extension but omits the matching bank-guarantee amendment or falls short of the extra 30-day margin, the submission fails eligibility under Article 29 of Decree No. 214/2025/ND-CP.
To prevent last-minute lapses, VNTender advises issuing e-GP extension notices at least 7 to 10 working days before expiry so bidders have adequate time to process bank amendments. Upon receiving guarantee endorsements linked to Form 04A or Form 04B under Circular No. 79/2025/TT-BTC, evaluators should verify the revised expiry date, original guarantee reference number, unconditional non-revocable wording, and authorized bank signatures.
Checklist for Managing E-HSDT and Bid Security Extensions
- Set automated calendar alerts at least 10 working days before E-HSDT expiry across active packages.
- Transmit formal extension requests via e-GP with an explicit response deadline for participating bidders.
- Verify every amended bid guarantee covers the extended E-HSDT validity period plus 30 additional calendar days.
- Release or return bid securities within 14 days when a bidder submits a valid written refusal to extend.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Clauses 5, 6, and 8, Article 14); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 26, 29, and Clause 16, Article 140); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025 (Forms 04A and 04B).