Appraisal, Petitions & e-GP

Online Purchasing on e-GP: Eligibility Thresholds and Electronic Ordering Workflow

Online Purchasing on e-GP: Eligibility Thresholds and Electronic Ordering Workflow
Operational guide to statutory thresholds, eligibility limits, and the four-step electronic ordering workflow from centralized procurement catalogs under Articles 103 and 104 of Decree 214/2025/ND-CP.

Key Takeaways

  • Governing Scope: Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Clause 4 Article 2, Articles 22, 103, and 104).
  • Key Benchmark: To deploy this mechanism validly, the approved procurement plan must designate online purchasing and satisfy two statutory conditions under Article 103 of Decree 214/2025/ND-CP.
  • Execution Control: Track supplier acceptance or rejection notices on e-GP within the mandatory 3-working-day response window.

01Regulatory Context & Core Scope

Budget-funded entities frequently confuse online quotation with online purchasing on Vietnam's e-GP platform. Under Clause 4, Article 2 of Decree 214/2025/ND-CP, online purchasing enables direct electronic procurement of goods or services from suppliers already awarded those exact items through centralized procurement, avoiding redundant competitive tendering.

To deploy this mechanism validly, the approved procurement plan must designate online purchasing and satisfy two statutory conditions under Article 103 of Decree 214/2025/ND-CP. First, package ceilings must not exceed VND 500 million for recurrent procurement budgets or VND 1 billion for investment projects.

02Core Regulatory Provisions & Conditions

Second, orders must fall within the active framework agreement term, or up to 24 months from contract effectiveness (or 24 months from award publication where the contract or framework agreement has not yet been disclosed under Article 22).

Article 104 sets out a four-step digital workflow on e-GP. Initially, the platform automatically populates eligible centralized-procurement items into an electronic catalog. Next, the Project Owner selects verified technical models and submits an online purchase order specifying exact quantities, awarded unit prices, shipping terms, delivery location, and payment schedule.

03Procedural Sequence & e-GP Execution

Upon order submission, e-GP automatically notifies the awarded centralized-procurement supplier. Under Article 104, that supplier must confirm acceptance or decline the order directly on the portal within 3 working days from receipt.

Once confirmed, the platform publishes the acceptance notice so the Project Owner can finalize contract signing and delivery immediately, trimming weeks from routine procurement cycles. If the supplier declines within allowed framework limits, the Project Owner retains clear documentation to re-route the order or revise the procurement method.

Pre-Order Verification for e-GP Online Purchasing

  • Verify that online purchasing is explicitly approved in the current contractor selection plan.
  • Check package ceilings against VND 500 million (recurrent budget) or VND 1 billion (investment project) limits.
  • Confirm the centralized framework agreement or 24-month post-award validity window remains open.
  • Specify exact technical models, freight charges, delivery points, and payment terms on the e-GP order form.
  • Track supplier acceptance or rejection notices on e-GP within the mandatory 3-working-day response window.

Legal Basis & Regulatory Scope

Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15); Decree 214/2025/ND-CP (Clause 4 Article 2, Articles 22, 103, and 104); Circular 79/2025/TT-BTC.

Filed under: Appraisal, Petitions & e-GP #Online Purchasing #e-GP Platform #Centralized Procurement #Decree 214/2025