Key Takeaways
- Governing Scope: Articles 8, 45, and 89 of Bidding Law 22/2023/QH15 (as amended by Law 90/2025/QH15); Articles 16, 18, 28, 33, 34, 120, 121, 138, and 140 of Decree 214/2025/ND-CP (as.
- Key Benchmark: Enforce publication windows: quotes at least 3 working days (10 days medical), plans and awards within 5 working days, and e-GP opening within 2 hours.
- Execution Control: Enforce Decree 349/2026/ND-CP petition rules: 3-working-day pre-closing E-HSMT filings, 7-working-day owner/authority rulings, and 2-working-day Council uploads.
01Regulatory Context & Core Scope
Since Decree 349/2026/ND-CP entered into force on 9 September 2026 amending key provisions of Decree 214/2025/ND-CP, procurement teams must align their schedules with several revised statutory deadlines. Distinguishing calendar days from working days helps Project Owners avoid procedural errors during appraisal, state audits, and petition reviews.
02Pricing Methodology & Cost Controls
At the planning and pricing stage, public e-GP quotation notices require at least 3 working days for standard goods and services (or 10 calendar days for pharmaceuticals, reagents, and medical devices) under Article 1 of Decree 349/2026/ND-CP; optional price updates run within 28 days before bid opening under Clause 1, Article 18 of Decree 214/2025/ND-CP; approved procurement plans publish within 5 working days; and post-plan package estimates publish at least 5 days (3 days for price-volatile goods) before bid closing under Clause 3, Article 13 of Circular 79/2025/TT-BTC.
Between E-HSMT issuance and bid opening under Article 28 of Decree 214/2025/ND-CP and Article 29 of Circular 79/2025/TT-BTC, minimum preparation time is 9 days for domestic works or mixed packages up to 20 billion VND, goods or non-consulting packages up to 10 billion VND, and direct-appointment-eligible packages tendered openly, or 18 days for larger domestic tenders (18 and 35 days internationally). Bidder clarification requests arrive at least 3 working days (5 working days internationally) before closing; Project Owner clarifications publish at least 2 working days prior; E-HSMT addenda publish at least 3 working days or 10 days ahead depending on package scale; bids open on e-GP within 2 hours of closing; and zero-bid deadline extensions under Article 16 of Decree 349/2026/ND-CP run at least 5 working days or 10 days.
03Independent Appraisal, Petitions & Audit Trails
For evaluation, award, and contract execution, Article 45 of Bidding Law 22/2023/QH15 (amended by Law 90/2025/QH15) and Clause 7, Article 18 of Decree 214/2025/ND-CP allow Project Owners to calibrate evaluation and appraisal durations in the procurement plan without a rigid 45-day cap. Award results or cancellations publish within 5 working days; Article 33 debriefing replies issue within 2 working days; unsuccessful bid securities release within 14 days; document verification runs 5 working days and contract finalization/signing 10 days under Forms 04A and 04B; contract disclosures publish within 5 working days; payments process in 14 days; and contract liquidation finishes within 45 days (up to 90 days for complex contracts).
During petition handling under Article 15 of Decree 349/2026/ND-CP amending Article 138 of Decree 214/2025/ND-CP, pre-closing E-HSMT petitions must reach the Project Owner at least 3 working days before closing, and award petitions arrive within 10 calendar days of e-GP result posting. First-tier Project Owner and Competent Person rulings take 7 working days; Petition Resolution Councils rule within 30 days (extendable by up to 10 days for complex issues); and the Standing Unit posts Council rulings within 2 working days.
Master Checklist of Statutory Procurement Timelines on e-GP
- Enforce publication windows: quotes at least 3 working days (10 days medical), plans and awards within 5 working days, and e-GP opening within 2 hours.
- Maintain minimum 9-day or 18-day domestic bid preparation, 2-working-day pre-closing clarifications, and 3-working-day or 10-day addendum cutoffs.
- Track post-award periods: 2 working days for debriefing replies, 5 working days for document verification, 14 days max for bid security release, and 5 working days for contract posting.
- Enforce Decree 349/2026/ND-CP petition rules: 3-working-day pre-closing E-HSMT filings, 7-working-day owner/authority rulings, and 2-working-day Council uploads.
Legal Basis & Regulatory Scope
Articles 8, 45, and 89 of Bidding Law 22/2023/QH15 (as amended by Law 90/2025/QH15); Articles 16, 18, 28, 33, 34, 120, 121, 138, and 140 of Decree 214/2025/ND-CP (as amended by Articles 1, 15, and 16 of Decree 349/2026/ND-CP); and Articles 12, 13, 29 and Section 18 E-BDL of Circular 79/2025/TT-BTC.