Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Articles 44 and 45); Governme.
- Key Benchmark: Export the draft e-GP webform BOQ to a spreadsheet and reconcile every work code and quantity against the approved estimate.
- Execution Control: Issue a formal E-HSMT amendment and extend closing dates promptly if discrepancies appear before bid closing.
01Regulatory Context & Core Scope
Across e-GP works tenders, post-opening pricing disputes frequently stem not from bidder error but from mismatches between the webform Bill of Quantities (BOQ), approved construction drawings, and the approved cost estimate. Such discrepancies commonly arise when drafters transcribe outdated spreadsheet schedules after final design review or omit ancillary scope items while carving a single package out of a master project estimate.
02Pricing Methodology & Cost Controls
Under Clause 2, Article 26 of Circular No. 79/2025/TT-BTC and Article 26 of Decree No. 214/2025/ND-CP, an E-HSMT published on e-GP must supply complete drawings, technical specifications, and an accurate BOQ so bidders can price on an equal footing. Before submitting the E-HSMT for approval, consultants must run a two-way check of item codes, material specs, measurement units, and quantities between the approved estimate workbook and the e-GP webform, paying special attention to unit mismatches such as square meters, cubic meters, metric tons, and kilograms.
When a bidder detects missing items or quantity gaps between the webform BOQ and attached drawings prior to closing, it should submit a clarification request via e-GP within the statutory pre-closing window under Article 45 of Law No. 22/2023/QH15. Upon confirming a valid error, the procuring entity and investor must issue an E-HSMT amendment, update the webform BOQ, and extend the closing deadline if the scope adjustment materially affects bid preparation.
03Procedural Sequence & e-GP Execution
If a discrepancy surfaces only after bid opening, the E-HSMT cannot be amended and evaluators must apply arithmetic error correction and deviation adjustment rules strictly under Article 31 of Decree No. 214/2025/ND-CP. Bidders must not arbitrarily insert extra lines into the standardized e-GP BOQ. Any quantities omitted relative to approved drawings are reconciled during contract negotiation and finalization using unit rates from the bid or approved estimate in line with the contract type.
Project reviews at Hoang Quan Construction Investment Development Consulting Co., Ltd. (VNTender) demonstrate that exporting the draft e-GP webform BOQ into a formula-based check sheet against the approved estimate before publishing the E-TBMT eliminates unit mismatches and dropped items. Recording this verification in an internal sign-off log with controlled drawing revision tags creates clear evidence for independent appraisal.
Pre-Publication e-GP Webform BOQ Reconciliation Steps
- Export the draft e-GP webform BOQ to a spreadsheet and reconcile every work code and quantity against the approved estimate.
- Verify unit consistency across the webform BOQ, cost-estimate breakdown, and construction drawing notes.
- Check general items, temporary site facilities, and safety-compliance line items so no ancillary scope is omitted.
- Issue a formal E-HSMT amendment and extend closing dates promptly if discrepancies appear before bid closing.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, 116/2025/QH15, 133/2025/QH15, and 142/2025/QH15 (Articles 44 and 45); Government Decree No. 214/2025/ND-CP dated 04/08/2025 (Articles 26, 29, and 31); Ministry of Finance Circular No. 79/2025/TT-BTC dated 04/08/2025 (Article 26 and works E-HSMT forms).