Key Takeaways
- Governing Scope: Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Articles 19, 78, 79, and 80); Government Decree No. 214/202.
- Key Benchmark: 90/2025/QH15 repealed Clause 1, Article 79 of Law on Procurement No.
- Execution Control: Archive signed independence declarations, confidentiality pledges, and independent appraisal reports to document clear accountability.
01Regulatory Context & Core Scope
Before Law No. 90/2025/QH15 took effect on 01/07/2025, many project investors delegated E-TBMT posting, E-HSMT clarification responses, and bid-verification notices almost entirely to procuring entities or hired consultants, signing final approvals largely on routine submission memos. Recent legislative reforms reorganized this governance chain, tying direct approval authority to ultimate investor accountability.
02Procedural Sequence & e-GP Execution
Specifically, Law No. 90/2025/QH15 repealed Clause 1, Article 79 of Law on Procurement No. 22/2023/QH15 covering procuring-entity duties in contractor selection and transferred core operational responsibilities directly into Article 78 on Investor Responsibilities. Under revised Article 78, the investor approves contractor selection plans, E-HSMT documents, and award results, while answering E-HSMT clarifications, issuing E-HSDT clarification requests, organizing appraisals, and executing contracts.
Where an investor lacks internal capacity and hires an external procurement consultancy, the consultancy establishes an evaluation panel satisfying Articles 19 and 80 of the Procurement Law. Law No. 90/2025/QH15 reinforced Article 80 by mandating honesty and objectivity from panel members and making them directly accountable to the investor for accurate E-HSMT drafting and bid evaluation findings.
03Independent Appraisal, Petitions & Audit Trails
Crucially, engaging an external consultant never shields the investor from statutory liability before the competent authority or state auditors. If an approved E-HSMT includes competition-restricting criteria or an erroneous evaluation report leads to award annulment, the investor remains legally responsible for the administrative decision, while the consultant bears contractual liability, damages, and professional sanctions within its contracted scope.
Accordingly, consulting contracts between investors and Hoang Quan Construction Investment Development Consulting Co., Ltd. (VNTender) establish dual-gate governance: every clarification draft, technical criterion check, and document-verification minute carries panel sign-off alongside investor compliance verification before publication on e-GP.
Governance Checklist When Engaging External Procurement Consultants
- Define explicit consultant deliverables in the contract, covering draft E-HSMT, clarification memos, and bid evaluation reports.
- Verify valid procurement practicing certificates for every evaluation panel member under Article 19 of the Procurement Law.
- Require formal investor sign-off before releasing E-HSMTs or clarification notices on e-GP.
- Archive signed independence declarations, confidentiality pledges, and independent appraisal reports to document clear accountability.
Legal Basis & Regulatory Scope
Law on Procurement No. 22/2023/QH15 as amended by Laws No. 57/2024/QH15, 90/2025/QH15, and 142/2025/QH15 (Articles 19, 78, 79, and 80); Government Decree No. 214/2025/ND-CP dated 04/08/2025; Ministry of Finance Circulars No. 79/2025/TT-BTC dated 04/08/2025 and No. 80/2025/TT-BTC dated 08/08/2025.